Poonam Celeste, Ghatkopar East

by PL7 Realty Pvt Ltd · Ghatkopar East, Mumbai 400077 · Map

Launched
Aug 20222 yrs 3 mths originally promised
Possession (MahaRERA)
Aug 2027Extended by 2 yrs 9 mths
Concrete structure
100%Nearing possession
Booked (free sale)
11 of 1292% · 16 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale11 booked out of 12 units

Rehab16 units for existing members

Total 28 units. Rehab units are not for sale.

Project facts

1 BHK
1
2 BHK
15
3 BHK
8
Other units
4
Total units
28
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
12
Rehab units
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services31%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 25%Dec 2025: Final finishes 25%Jul 2026: Final finishes 25%Oct 2026: Final finishes 31%Excavation 100%Concrete structure (RCC) 100%Final finishes 31%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%31%11
100%100%25%10
100%100%25%9
100%100%25%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400077

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400077
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 3 mths3 yrs 6 mths
Possession date extendedBy 2 yrs 9 mths2 of 6
Possession date (MahaRERA)Aug 2027Dec 2026
Concrete structure (RCC)100%90%
Units booked (free sale)92%53%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Poonam Celeste by PL7 Realty Pvt Ltd is a 28-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in August 2022 with possession due in August 2027. 11 units booked out of 12 units for sale. The concrete structure (RCC) is complete.

Read full summary

Poonam Celeste is a BMC-sanctioned project by PL7 Realty Pvt Ltd in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800046581. It was launched in August 2022. It has 28 units in 1 building: 24 homes (1, 2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 28 units, 12 are for sale and 16 are rehab units for existing members.

Its registered possession date is August 2027, extended by 2 years 9 months from the original November 2024. Construction: excavation complete, structure (RCC) complete, final finishes 31% complete.

11 units booked out of 12 units for sale (92%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from November 2025 to August 2027.