Kakkad, Ghatkopar East

by Silver Land Developers Private Limited · Ghatkopar East, Mumbai 400077 · Map

Launched
Jun 20224 yrs 6 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked
23 of 4452%
Buildings
11.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
10
4 BHK
34
Total units
44
Buildings
1
Land
1.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 10%Dec 2025: Final finishes 10%Jul 2026: Final finishes 10%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 100%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%23
100%100%10%23
100%100%10%23
100%100%10%20

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400077

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400077
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 6 mths3 yrs 5 mths
Possession date extendedNo3 of 5
Possession date (MahaRERA)Dec 2026Dec 2026
Concrete structure (RCC)100%80%
Units booked52%92%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Kakkad by Silver Land Developers Private Limited is a 44-unit SRA-sanctioned project in Ghatkopar East, Mumbai 400077, launched in June 2022 with possession due in December 2026. 23 units booked out of total 44 units. The concrete structure (RCC) is complete.

Read full summary

Kakkad is an SRA-sanctioned project by Silver Land Developers Private Limited in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800045780. It was launched in June 2022. It has 44 units in 1 building, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.

23 units booked out of total 44 units (52%).