Sarvasya, Ghatkopar East

Lapsed

by Maverick Realtors · Ghatkopar East, Mumbai 400077 · Map

Launched
Aug 20223 yrs 7 mths promised
Possession (MahaRERA)
Mar 2026Not extendedWhat does Lapsed mean?
Concrete structure
15%Mid-construction
Booked (free sale)
11 of 1292% · 16 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale11 booked out of 12 units

Rehab16 units for existing members

Total 28 units. Rehab units are not for sale.

Project facts

1 BHK
2
2 BHK
11
3 BHK
15
Total units
28
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
12
Rehab units
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)15%
Finishes, lifts and services94%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 5%Dec 2025: Concrete structure (RCC) 5%Jul 2026: Concrete structure (RCC) 5%Oct 2026: Concrete structure (RCC) 15%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 94%Excavation 100%Final finishes 94%Concrete structure (RCC) 15%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%15%94%11
100%5%0%5
100%5%0%–
100%5%0%2

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400077

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400077
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 7 mths3 yrs 6 mths
Possession date extendedNo3 of 6
Possession date (MahaRERA)Mar 2026Apr 2027
Concrete structure (RCC)15%100%
Units booked (free sale)92%53%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Sarvasya by Maverick Realtors is a 28-unit SRA-sanctioned project in Ghatkopar East, Mumbai 400077, launched in August 2022; its MahaRERA registration has lapsed. 11 units booked out of 12 units for sale. The concrete structure (RCC) is 15% complete.

Read full summary

Sarvasya is an SRA-sanctioned project by Maverick Realtors in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800046693. It was launched in August 2022. It has 28 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 28 units, 12 are for sale and 16 are rehab units for existing members.

Possession was due in March 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 15% complete, final finishes 94% complete.

11 units booked out of 12 units for sale (92%). Since the July 2026 update, 6 more units have been booked and the reported concrete structure (RCC) has gone from 5% to 15%.