- Launched
- Sep 20226 yrs 3 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 86 of 8997% · 38 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale86 booked out of 89 units
Rehab38 units for existing members
Total 127 units. Rehab units are not for sale.
Project facts
- 1 RK
- 35
- 1 BHK
- 67
- 2 BHK
- 19
- Other units
- 6
- Total units
- 127
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 89
- Rehab units
- 38
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 86 | |
| 100% | 100% | 95% | 85 | |
| 100% | 100% | 95% | 75 | |
| 100% | 100% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400060
Projects with 60–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 3 mths | 3 yrs 6 mths |
| Possession date extended | No | 2 of 4 |
| Possession date (MahaRERA) | Dec 2028 | Jun 2027 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 97% | 66% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Uk Iona, Jogeshwari East
- AIM Garden, Jogeshwari East
- Shraddha West Residency, Jogeshwari East
- Ashtavinayak Apartments, Jogeshwari East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Uk Iona | November 2022 | Dec 2026 – Dec 2027 | 100% | 156 units booked out of total 244 units |
| AIM Garden | December 2022 | July 2029 | 100% | 111 units booked out of 163 units for sale |
| Shraddha West Residency | March 2023 | December 2027 | 93% | 52 units booked out of total 106 units |
| Ashtavinayak Apartments | March 2023 | June 2026 | 100% | 158 units booked out of total 173 units |
About this project
Aim Horizon by A.M Enterprises is a 127-unit SRA-sanctioned project in Jogeshwari East, Mumbai 400060, launched in September 2022 with possession due in December 2028. 86 units booked out of 89 units for sale. The concrete structure (RCC) is complete.
Read full summary
Aim Horizon is an SRA-sanctioned project by A.M Enterprises in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800047046. It was launched in September 2022. It has 127 units in 1 building: 121 homes (1 RK, 1 BHK and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 127 units, 89 are for sale and 38 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
86 units booked out of 89 units for sale (97%). Since the July 2026 update, 1 more unit has been booked.