Shraddha West Residency, Jogeshwari East

by Shraddha Buildcon Pvt Ltd · Jogeshwari East, Mumbai 400060 · Map

Launched
Mar 20232 yrs 9 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 2 yrs
Concrete structure
93%Mid-construction
Booked
52 of 10649% · 51 in Jul 2026
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
105
Total units
106
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)93%
Finishes, lifts and services5%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 22%Dec 2025: Concrete structure (RCC) 93%Jul 2026: Concrete structure (RCC) 98%Oct 2026: Concrete structure (RCC) 93%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 5%Oct 2026: Final finishes 5%Excavation 100%Concrete structure (RCC) 93%Final finishes 5%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%93%5%52
100%98%5%51
100%93%0%53
100%22%0%44

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400060

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400060
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 9 mths4 yrs 4 mths
Possession date extendedBy 2 yrs1 of 5
Possession date (MahaRERA)Dec 2027Dec 2026
Concrete structure (RCC)93%100%
Units booked49%91%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Shraddha West Residency by Shraddha Buildcon Pvt Ltd is a 106-unit SRA-sanctioned project in Jogeshwari East, Mumbai 400060, launched in March 2023 with possession due in December 2027. 52 units booked out of total 106 units. The concrete structure (RCC) is 93% complete.

Read full summary

Shraddha West Residency is an SRA-sanctioned project by Shraddha Buildcon Pvt Ltd in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800049859. It was launched in March 2023. It has 106 units in 1 building, with 1 RK and 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 2 years from the original December 2025. Construction: excavation complete, structure (RCC) 93% complete, final finishes 5% complete.

52 units booked out of total 106 units (49%). Since the July 2026 update, 1 more unit has been booked, the reported concrete structure (RCC) has gone from 98% to 93% and the possession date has moved from December 2026 to December 2027.

Shraddha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA53
Total units across these projects9,707
Completed without extending the possession date16
Completed after an extension4
Lapsed5
Under construction28
Possession date extended on the builder's application18
Typical time from launch to 100% structure4 years
MahaRERA complaints (filed by or against the builder), all Shraddha projects14 (11 of 53 projects)

See all Shraddha projects →