Shraddha West Residency, Jogeshwari East
by Shraddha Buildcon Pvt Ltd · Jogeshwari East, Mumbai 400060 · Map
- Launched
- Mar 20232 yrs 9 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 2 yrs
- Concrete structure
- 93%Mid-construction
- Booked
- 52 of 10649% · 51 in Jul 2026
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 1
- 1 BHK
- 105
- Total units
- 106
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 93% | 5% | 52 | |
| 100% | 98% | 5% | 51 | |
| 100% | 93% | 0% | 53 | |
| 100% | 22% | 0% | 44 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400060
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 4 yrs 4 mths |
| Possession date extended | By 2 yrs | 1 of 5 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2026 |
| Concrete structure (RCC) | 93% | 100% |
| Units booked | 49% | 91% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Ashtavinayak Apartments, Jogeshwari East
- Devbhoomi, Jogeshwari East
- AIM Garden, Jogeshwari East
- Uk Iona, Jogeshwari East
- Aim Horizon, Jogeshwari East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ashtavinayak Apartments | March 2023 | June 2026 | 100% | 158 units booked out of total 173 units |
| Devbhoomi | May 2023 | December 2026 | 90% | 90 units booked out of 92 units for sale |
| AIM Garden | December 2022 | July 2029 | 100% | 111 units booked out of 163 units for sale |
| Uk Iona | November 2022 | Dec 2026 – Dec 2027 | 100% | 156 units booked out of total 244 units |
| Aim Horizon | September 2022 | December 2028 | 100% | 86 units booked out of 89 units for sale |
About this project
Shraddha West Residency by Shraddha Buildcon Pvt Ltd is a 106-unit SRA-sanctioned project in Jogeshwari East, Mumbai 400060, launched in March 2023 with possession due in December 2027. 52 units booked out of total 106 units. The concrete structure (RCC) is 93% complete.
Read full summary
Shraddha West Residency is an SRA-sanctioned project by Shraddha Buildcon Pvt Ltd in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800049859. It was launched in March 2023. It has 106 units in 1 building, with 1 RK and 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 2 years from the original December 2025. Construction: excavation complete, structure (RCC) 93% complete, final finishes 5% complete.
52 units booked out of total 106 units (49%). Since the July 2026 update, 1 more unit has been booked, the reported concrete structure (RCC) has gone from 98% to 93% and the possession date has moved from December 2026 to December 2027.
Shraddha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 53 |
|---|---|
| Total units across these projects | 9,707 |
| Completed without extending the possession date | 16 |
| Completed after an extension | 4 |
| Lapsed | 5 |
| Under construction | 28 |
| Possession date extended on the builder's application | 18 |
| Typical time from launch to 100% structure | 4 years |
| MahaRERA complaints (filed by or against the builder), all Shraddha projects | 14 (11 of 53 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.