Apex Green Wood, Borivali East
Ready to moveLapsed
by Apex Infratec · Borivali East, Mumbai 400066 · Map
- Launched
- Oct 20223 yrs 8 mths promised
- Possession (MahaRERA)
- Jun 2026Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 149 of 20672% · 44 rehab units
- Buildings
- 30.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale149 booked out of 206 units
Rehab44 units for existing members
Total 250 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 115
- 2 BHK
- 132
- 3 BHK
- 3
- Total units
- 250
- Buildings
- 3
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 206
- Rehab units
- 44
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 149 | |
| 100% | 100% | 100% | 149 | |
| 100% | 60% | 0% | 149 | |
| 100% | 60% | 0% | 69 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400066
Projects with 100–500 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 8 mths | 4 yrs 6 mths |
| Possession date extended | No | 1 of 4 |
| Possession date (MahaRERA) | Jun 2026 | Jan 2027 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 72% | 86% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Sheetal Regalia, Borivali East
- RAGHAV Paradise, Borivali East
- Rivali Park - Sunburst, Borivali East
- Magathane Press Enclave Chsl, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sheetal Regalia | December 2022 | December 2026 | 47% | 233 units booked out of 238 units for sale |
| RAGHAV Paradise | May 2022 | December 2025 | 100% | 118 units booked out of total 197 units |
| Rivali Park - Sunburst | April 2023 | August 2028 | 100% | 263 units booked out of total 277 units |
| Magathane Press Enclave Chsl | April 2022 | March 2027 | 100% | 72 units booked out of 93 units for sale |
About this project
Apex Green Wood by Apex Infratec is a 250-unit MHADA-sanctioned project in Borivali East, Mumbai 400066, launched in October 2022; its MahaRERA registration has lapsed. 149 units booked out of 206 units for sale. The concrete structure (RCC) is complete.
Read full summary
Apex Green Wood is a MHADA-sanctioned project by Apex Infratec in Borivali East, Mumbai 400066, registered with MahaRERA as P51800047381. It was launched in October 2022. It has 250 units in 3 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 250 units, 206 are for sale and 44 are rehab units for existing members.
Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
149 units booked out of 206 units for sale (72%).