Shubh Elanza, Vikhroli

by Shubh Vastu Lifespace LLP · Vikhroli, Mumbai 400083 · Map

Launched
Nov 20223 yrs 9 mths originally promised
Possession (MahaRERA)
Feb 2027Extended by 6 mths
Concrete structure
100%Nearing possession
Booked (free sale)
137 of 14197% · 31 rehab units
Buildings
20.2 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale137 booked out of 141 units

Rehab31 units for existing members

Total 172 units. Rehab units are not for sale.

Project facts

1 BHK
103
2 BHK
51
Other units
18
Total units
172
Buildings
2
Land
0.2 acres
Phases
1
MahaRERA complaints
2
Free-sale units
141
Rehab units
31

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services45%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 56%Dec 2025: Concrete structure (RCC) 96%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 2%Jul 2026: Final finishes 23%Oct 2026: Final finishes 45%Excavation 100%Concrete structure (RCC) 100%Final finishes 45%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%45%137
100%100%23%138
100%96%2%136
100%56%0%112

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400083

Projects with 70–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400083
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths3 yrs 11 mths
Possession date extendedBy 6 mths0 of 6
Possession date (MahaRERA)Feb 2027Dec 2026
Concrete structure (RCC)100%100%
Units booked (free sale)97%94%
MahaRERA complaints (filed by or against the builder)20

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shubh Elanza by Shubh Vastu Lifespace LLP is a 172-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in November 2022 with possession due in February 2027. 137 units booked out of 141 units for sale. The concrete structure (RCC) is complete.

Read full summary

Shubh Elanza is a MHADA-sanctioned project by Shubh Vastu Lifespace LLP in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800047511. It was launched in November 2022. It has 172 units in 2 buildings: 154 homes (1 and 2 BHK) and 18 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 172 units, 141 are for sale and 31 are rehab units for existing members.

Its registered possession date is February 2027, extended by 6 months from the original August 2026. Construction: excavation complete, structure (RCC) complete, final finishes 45% complete.

137 units booked out of 141 units for sale (97%). Since the July 2026 update, the possession date has moved from August 2026 to February 2027.