Shubh Elanza, Vikhroli
by Shubh Vastu Lifespace LLP · Vikhroli, Mumbai 400083 · Map
- Launched
- Nov 20223 yrs 9 mths originally promised
- Possession (MahaRERA)
- Feb 2027Extended by 6 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 137 of 14197% · 31 rehab units
- Buildings
- 20.2 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale137 booked out of 141 units
Rehab31 units for existing members
Total 172 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 103
- 2 BHK
- 51
- Other units
- 18
- Total units
- 172
- Buildings
- 2
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 141
- Rehab units
- 31
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 45% | 137 | |
| 100% | 100% | 23% | 138 | |
| 100% | 96% | 2% | 136 | |
| 100% | 56% | 0% | 112 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400083
Projects with 70–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 3 yrs 11 mths |
| Possession date extended | By 6 mths | 0 of 6 |
| Possession date (MahaRERA) | Feb 2027 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 97% | 94% |
| MahaRERA complaints (filed by or against the builder) | 2 | 0 |
The 6 projects
- Natasha Atlantis, Vikhroli
- Vrindavan Elite, Vikhroli
- Swastik Tulip, Vikhroli
- Puneet Brahmand, Vikhroli
- Shraddha Palladium, Vikhroli
- Vista Meadows, Vikhroli
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Natasha Atlantis | November 2022 | December 2028 | 100% | 85 units booked out of 191 units for sale |
| Vrindavan Elite | December 2022 | October 2026 | 100% | 91 units booked out of 92 units for sale |
| Swastik Tulip | January 2023 | December 2026 | 100% | 118 units booked out of total 120 units |
| Puneet Brahmand | September 2022 | December 2026 | 54% | 106 units booked out of total 106 units |
| Shraddha Palladium | January 2023 | December 2026 | 53% | 190 units booked out of 212 units for sale |
| Vista Meadows | August 2022 | December 2025 | 100% | 87 units booked out of total 99 units |
About this project
Shubh Elanza by Shubh Vastu Lifespace LLP is a 172-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in November 2022 with possession due in February 2027. 137 units booked out of 141 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shubh Elanza is a MHADA-sanctioned project by Shubh Vastu Lifespace LLP in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800047511. It was launched in November 2022. It has 172 units in 2 buildings: 154 homes (1 and 2 BHK) and 18 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 172 units, 141 are for sale and 31 are rehab units for existing members.
Its registered possession date is February 2027, extended by 6 months from the original August 2026. Construction: excavation complete, structure (RCC) complete, final finishes 45% complete.
137 units booked out of 141 units for sale (97%). Since the July 2026 update, the possession date has moved from August 2026 to February 2027.