Skip to main content

Vista Meadows, Vikhroli

Ready to moveLapsed

by Padmalaxmi Estates LLP · Vikhroli, Mumbai 400083 · Map

Launched
Aug 20223 yrs 4 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
87 of 9988%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
85
2 BHK
14
Total units
99
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 60%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%87
100%100%90%–
100%100%90%–
100%100%60%87

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400083

Projects with 40–200 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400083
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths3 yrs 9 mths
Possession date extendedNo3 of 5
Possession date (MahaRERA)Dec 2025Dec 2026
Concrete structure (RCC)100%83%
Units booked88%97%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Vista Meadows by Padmalaxmi Estates LLP is a 99-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in August 2022; its MahaRERA registration has lapsed. 87 units booked out of total 99 units. The concrete structure (RCC) is complete.

Read full summary

Vista Meadows is a MHADA-sanctioned project by Padmalaxmi Estates LLP in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800046474. It was launched in August 2022. It has 99 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

87 units booked out of total 99 units (88%).