Rushabh Kiran, Ghatkopar East

Ready to move

by Rushabhkiran Chs Ltd · Ghatkopar East, Mumbai 400077 · Map

Launched
Dec 20223 yrs originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
100%Ready to move
Booked (free sale)
11 of 1292% · 30 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale11 booked out of 12 units

Rehab30 units for existing members

Total 42 units. Rehab units are not for sale.

Project facts

1 BHK
11
2 BHK
20
3 BHK
11
Total units
42
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
12
Rehab units
30

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jul 2026Oct 2026Dec 2024: Excavation 95%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 35%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%11
100%100%100%11
95%35%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400077

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400077
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs3 yrs 10 mths
Possession date extendedBy 1 yr3 of 6
Possession date (MahaRERA)Dec 2026Nov 2027
Concrete structure (RCC)100%90%
Units booked (free sale)92%46%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Rushabh Kiran by Rushabhkiran Chs Ltd is a 42-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in December 2022 with possession due in December 2026. 11 units booked out of 12 units for sale. The concrete structure (RCC) is complete.

Read full summary

Rushabh Kiran is a BMC-sanctioned project by Rushabhkiran Chs Ltd in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800048043. It was launched in December 2022. It has 42 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 42 units, 12 are for sale and 30 are rehab units for existing members.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

11 units booked out of 12 units for sale (92%).