Shree Pinal Project, Ghatkopar East
by Pinal Realty LLP · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Feb 2023First of 2 phases
- Possession (MahaRERA)
- Nov 2027 – Apr 2028Extended in 1 of 2 phases
- Concrete structure
- 100%Weighted across 2 phases
- Booked (free sale)
- 29 of 3485% · 39 rehab units
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale29 booked out of 34 units
Rehab39 units for existing members
Land-owner share1 unit, not for sale
Total 74 units. Rehab and land-owner units are not for sale.
Project facts
- 1 RK
- 2
- 1 BHK
- 10
- 2 BHK
- 20
- 3 BHK
- 21
- Other units
- 21
- Total units
- 74
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 2
- MahaRERA complaints
- 0
- Free-sale units
- 34
- Rehab units
- 39
- Land-owner share (not for sale)
- 1
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Shree Pinal Project A Ready to move | P51800049614 | 0 | 100% | 37% | |
| Shree Pinal Project B Nearing possession | P51800051150 | 53 | 100% | 40% |
Show updates by phase
Shree Pinal Project A (P51800049614)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 90% | 100% | 90% | 7 | |
| 90% | 100% | 0% | 2 | |
| 90% | 100% | 0% | – | |
| 90% | 100% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Shree Pinal Project B (P51800051150)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | 22 | |
| 100% | 85% | 0% | – | |
| 100% | 85% | 0% | – | |
| 100% | 85% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 4 similar projects in PIN 400077
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 1 mth | 3 yrs 5 mths |
| Possession date extended | Yes | 2 of 4 |
| Possession date (MahaRERA) | Nov 2027 – Apr 2028 | Jun 2027 |
| Concrete structure (RCC) | 100% | 69% |
| Units booked (free sale) | 85% | 61% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Rushabh Kiran, Ghatkopar East
- Kevli Plaza – A Wing And Kevli Darshan – B Wing, Ghatkopar East
- Nav Indralok, Ghatkopar East
- Jai Arihant, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rushabh Kiran | December 2022 | December 2026 | 100% | 11 units booked out of 12 units for sale |
| Kevli Plaza – A Wing And Kevli Darshan – B Wing | May 2023 | December 2028 | 63% | 26 units booked out of 67 units for sale |
| Nav Indralok | June 2023 | December 2026 | 75% | 14 units booked out of 17 units for sale |
| Jai Arihant | August 2023 | December 2027 | 50% | 11 units booked out of total 75 units |
About this project
Shree Pinal Project by Pinal Realty LLP is a 74-unit SRA-sanctioned project in Ghatkopar East, Mumbai 400077, registered with MahaRERA in 2 phases, with possession dates from November 2027 to April 2028. 29 units booked out of 34 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shree Pinal Project is an SRA-sanctioned project by Pinal Realty LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as 2 phases (P51800049614, P51800051150). The first phase was launched in February 2023. Together the phases have 74 units in 2 buildings: 53 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 21 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA. Of the 74 units, 34 are for sale, 39 are rehab units for existing members and 1 is the land-owner's share, not for sale.
The phases' registered possession dates run from November 2027 to April 2028; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 83% complete. Both phases have their structure complete.
29 units booked out of 34 units for sale (85%).