Shree Pinal Project, Ghatkopar East

by Pinal Realty LLP · Ghatkopar East, Mumbai 400077 · Map

Launched
Feb 2023First of 2 phases
Possession (MahaRERA)
Nov 2027 – Apr 2028Extended in 1 of 2 phases
Concrete structure
100%Weighted across 2 phases
Booked (free sale)
29 of 3485% · 39 rehab units
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale29 booked out of 34 units

Rehab39 units for existing members

Land-owner share1 unit, not for sale

Total 74 units. Rehab and land-owner units are not for sale.

Project facts

1 RK
2
1 BHK
10
2 BHK
20
3 BHK
21
Other units
21
Total units
74
Buildings
2
Land
0.4 acres
Phases
2
MahaRERA complaints
0
Free-sale units
34
Rehab units
39
Land-owner share (not for sale)
1

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Shree Pinal Project A
Ready to move
P518000496140100%37%
Shree Pinal Project B
Nearing possession
P5180005115053100%40%
Show updates by phase

Shree Pinal Project A (P51800049614)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%100%90%7
90%100%0%2
90%100%0%–
90%100%0%0

"–" means MahaRERA shows no figure for that update.

Shree Pinal Project B (P51800051150)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%22
100%85%0%–
100%85%0%–
100%85%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation97%
Concrete structure (slabs)100%
Finishes, lifts and services83%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 97%Dec 2025: Excavation 97%Jul 2026: Excavation 97%Oct 2026: Excavation 97%Dec 2024: Concrete structure (RCC) 89%Dec 2025: Concrete structure (RCC) 89%Jul 2026: Concrete structure (RCC) 89%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 83%Concrete structure (RCC) 100%Excavation 97%Final finishes 83%

How to read construction stages

Compared with 4 similar projects in PIN 400077

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400077
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 1 mth3 yrs 5 mths
Possession date extendedYes2 of 4
Possession date (MahaRERA)Nov 2027 – Apr 2028Jun 2027
Concrete structure (RCC)100%69%
Units booked (free sale)85%61%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Shree Pinal Project by Pinal Realty LLP is a 74-unit SRA-sanctioned project in Ghatkopar East, Mumbai 400077, registered with MahaRERA in 2 phases, with possession dates from November 2027 to April 2028. 29 units booked out of 34 units for sale. The concrete structure (RCC) is complete.

Read full summary

Shree Pinal Project is an SRA-sanctioned project by Pinal Realty LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as 2 phases (P51800049614, P51800051150). The first phase was launched in February 2023. Together the phases have 74 units in 2 buildings: 53 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 21 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA. Of the 74 units, 34 are for sale, 39 are rehab units for existing members and 1 is the land-owner's share, not for sale.

The phases' registered possession dates run from November 2027 to April 2028; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 83% complete. Both phases have their structure complete.

29 units booked out of 34 units for sale (85%).