71P, Borivali East
by Living Habitats Private Limited · Borivali East, Mumbai 400066 · Map
- Launched
- Jun 20232 yrs 3 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr 3 mths
- Concrete structure
- 41%Mid-construction
- Booked (free sale)
- 21 of 3462% · 26 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale21 booked out of 34 units
Rehab26 units for existing members
Total 60 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 41
- 3 BHK
- 15
- 4 BHK
- 1
- Other units
- 3
- Total units
- 60
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 34
- Rehab units
- 26
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 41% | 25% | 21 | |
| 100% | 41% | 25% | 22 | |
| 100% | 18% | 0% | 19 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400066
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 3 mths | 3 yrs 5 mths |
| Possession date extended | By 1 yr 3 mths | 2 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2026 |
| Concrete structure (RCC) | 41% | 98% |
| Units booked (free sale) | 62% | 79% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Balaji Darshan, Borivali East
- Arvind Niwas, Borivali East
- Abundanttiafull - By Bholas, Borivali East
- The Grand Residences, Borivali East
- Shree Krupa Chsl, Borivali East
- Ashtha Buoyancy - IBTC Borivali East, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Balaji Darshan | June 2023 | December 2027 | 100% | 12 units booked out of 14 units for sale |
| Arvind Niwas | August 2023 | June 2026 | 100% | 26 units booked out of 26 units for sale |
| Abundanttiafull - By Bholas | September 2023 | June 2026 | 89% | 21 units booked out of 60 units for sale |
| The Grand Residences | October 2023 | December 2027 | 40% | 76 units booked out of total 104 units |
| Shree Krupa Chsl | January 2023 | December 2026 | 100% | 48 units booked out of total 51 units |
| Ashtha Buoyancy - IBTC Borivali East | December 2022 | December 2026 | 97% | 16 units booked out of 88 units for sale |
About this project
71P by Living Habitats Private Limited is a 60-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in June 2023 with possession due in December 2026. 21 units booked out of 34 units for sale. The concrete structure (RCC) is 41% complete.
Read full summary
71P is a BMC-sanctioned project by Living Habitats Private Limited in Borivali East, Mumbai 400066, registered with MahaRERA as P51800051382. It was launched in June 2023. It has 60 units in 1 building: 57 homes (2, 3 and 4 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 60 units, 34 are for sale and 26 are rehab units for existing members.
Its registered possession date is December 2026, extended by 1 year 3 months from the original September 2025. Construction: excavation complete, structure (RCC) 41% complete, final finishes 25% complete.
21 units booked out of 34 units for sale (62%).