Megha Edge- Red Rose, Borivali West

Ready to moveLapsed

by Megha Lakshmi Enterprise · Borivali West, Mumbai 400092 · Map

Launched
Sep 20223 yrs originally promised
Possession (MahaRERA)
Jun 2026Extended by 9 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
5 of 862%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 8 units

Land-owner share16 units, not for sale

Total 24 units. Land-owner units are not for sale.

Project facts

1 BHK
7
2 BHK
14
Other units
3
Total units
24
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
8
Land-owner share (not for sale)
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 98%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%5
100%100%98%5
100%0%0%5
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400092

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs3 yrs 4 mths
Possession date extendedBy 9 mths1 of 4
Possession date (MahaRERA)Jun 2026May 2027
Concrete structure (RCC)100%40%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Megha Edge- Red Rose by Megha Lakshmi Enterprise is a 24-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in September 2022; its MahaRERA registration has lapsed. 5 units booked out of 8 units for sale. The concrete structure (RCC) is complete.

Read full summary

Megha Edge- Red Rose is a BMC-sanctioned project by Megha Lakshmi Enterprise in Borivali West, Mumbai 400092, registered with MahaRERA as P51800046888. It was launched in September 2022. It has 24 units in 1 building: 21 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 24 units, 8 are for sale and 16 are the land-owner's share, not for sale.

Possession was due in June 2026, after an extension of 9 months from the original September 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

5 units booked out of 8 units for sale (62%).