Goodwill Co Operative Housing Society Ltd, Bhandup East

Ready to moveLapsed

by Trimurti Buildcon Builders And Developers · Bhandup East, Mumbai 400042 · Map

Launched
Feb 20232 yrs 3 mths originally promised
Possession (MahaRERA)
May 2026Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
47 of 5389% · 3 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale47 booked out of 53 units

Rehab3 units for existing members

Total 56 units. Rehab units are not for sale.

Project facts

1 BHK
35
2 BHK
21
Total units
56
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
53
Rehab units
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 80%Jul 2026: Final finishes 90%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%47
100%100%90%22
100%100%80%20
100%100%0%11

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400042

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400042
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 3 mths3 yrs 3 mths
Possession date extendedBy 1 yr2 of 5
Possession date (MahaRERA)May 2026Dec 2026
Concrete structure (RCC)100%90%
Units booked (free sale)89%54%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Goodwill Co Operative Housing Society Ltd by Trimurti Buildcon Builders And Developers is a 56-unit BMC-sanctioned project in Bhandup East, Mumbai 400042, launched in February 2023; its MahaRERA registration has lapsed. 47 units booked out of 53 units for sale. The concrete structure (RCC) is complete.

Read full summary

Goodwill Co Operative Housing Society Ltd is a BMC-sanctioned project by Trimurti Buildcon Builders And Developers in Bhandup East, Mumbai 400042, registered with MahaRERA as P51800049604. It was launched in February 2023. It has 56 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 56 units, 53 are for sale and 3 are rehab units for existing members.

Possession was due in May 2026, after an extension of 1 year from the original May 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

47 units booked out of 53 units for sale (89%). Since the July 2026 update, 25 more units have been booked.