Skip to main content

Shivmangal Residency, Bhandup East

Ready to move

by Shraddha Landmark Private Limited · Bhandup East, Mumbai 400042 · Map

Launched
Jun 20232 yrs 11 mths originally promised
Possession (MahaRERA)
Aug 2026Extended by 3 mths
Concrete structure
100%Ready to move
Booked (free sale)
5 of 1436% · 16 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 14 units

Rehab16 units for existing members

Total 30 units. Rehab units are not for sale.

Project facts

2 BHK
30
Total units
30
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
14
Rehab units
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 60%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%5
100%100%100%2
100%75%0%–
100%60%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400042

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400042
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 11 mths3 yrs 6 mths
Possession date extendedBy 3 mths2 of 6
Possession date (MahaRERA)Aug 2026Jul 2027
Concrete structure (RCC)100%95%
Units booked (free sale)36%62%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shivmangal Residency by Shraddha Landmark Private Limited is a 30-unit BMC-sanctioned project in Bhandup East, Mumbai 400042, launched in June 2023 with possession due in August 2026. 5 units booked out of 14 units for sale. The concrete structure (RCC) is complete.

Read full summary

Shivmangal Residency is a BMC-sanctioned project by Shraddha Landmark Private Limited in Bhandup East, Mumbai 400042, registered with MahaRERA as P51800051741. It was launched in June 2023. It has 30 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 30 units, 14 are for sale and 16 are rehab units for existing members.

Possession was due in August 2026, after an extension of 3 months from the original May 2026. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

5 units booked out of 14 units for sale (36%). Since the July 2026 update, 3 more units have been booked.

Shraddha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA53
Total units across these projects9,707
Completed without extending the possession date16
Completed after an extension4
Lapsed5
Under construction28
Possession date extended on the builder's application18
Typical time from launch to 100% structure4 years
MahaRERA complaints (filed by or against the builder), all Shraddha projects14 (11 of 53 projects)

See all Shraddha projects →