Shivmangal Residency, Bhandup East
Ready to move
by Shraddha Landmark Private Limited · Bhandup East, Mumbai 400042 · Map
- Launched
- Jun 20232 yrs 11 mths originally promised
- Possession (MahaRERA)
- Aug 2026Extended by 3 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 5 of 1436% · 16 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 14 units
Rehab16 units for existing members
Total 30 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 30
- Total units
- 30
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 14
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 5 | |
| 100% | 100% | 100% | 2 | |
| 100% | 75% | 0% | – | |
| 100% | 60% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400042
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 11 mths | 3 yrs 6 mths |
| Possession date extended | By 3 mths | 2 of 6 |
| Possession date (MahaRERA) | Aug 2026 | Jul 2027 |
| Concrete structure (RCC) | 100% | 95% |
| Units booked (free sale) | 36% | 62% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Isha Vasyam, Bhandup East
- Bhumi Akshay, Bhandup East
- Rajshree Ashish Co-Operative Housing Society Limited, Bhandup East
- Ramchandra Enclave, Bhandup East
- Goodwill Co Operative Housing Society Ltd, Bhandup East
- Karuna Sagar Chs Ltd, Bhandup East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Isha Vasyam | July 2023 | June 2027 | 100% | 10 units booked out of 17 units for sale |
| Bhumi Akshay | July 2023 | June 2028 | 35% | 11 units booked out of total 17 units |
| Rajshree Ashish Co-Operative Housing Society Limited | March 2023 | January 2028 | 90% | 13 units booked out of 14 units for sale |
| Ramchandra Enclave | September 2023 | July 2027 | 100% | 7 units booked out of 14 units for sale |
| Goodwill Co Operative Housing Society Ltd | February 2023 | May 2026 | 100% | 47 units booked out of 53 units for sale |
| Karuna Sagar Chs Ltd | December 2022 | May 2025 | 0% | 14 units booked out of total 26 units |
About this project
Shivmangal Residency by Shraddha Landmark Private Limited is a 30-unit BMC-sanctioned project in Bhandup East, Mumbai 400042, launched in June 2023 with possession due in August 2026. 5 units booked out of 14 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shivmangal Residency is a BMC-sanctioned project by Shraddha Landmark Private Limited in Bhandup East, Mumbai 400042, registered with MahaRERA as P51800051741. It was launched in June 2023. It has 30 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 30 units, 14 are for sale and 16 are rehab units for existing members.
Possession was due in August 2026, after an extension of 3 months from the original May 2026. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
5 units booked out of 14 units for sale (36%). Since the July 2026 update, 3 more units have been booked.
Shraddha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 53 |
|---|---|
| Total units across these projects | 9,707 |
| Completed without extending the possession date | 16 |
| Completed after an extension | 4 |
| Lapsed | 5 |
| Under construction | 28 |
| Possession date extended on the builder's application | 18 |
| Typical time from launch to 100% structure | 4 years |
| MahaRERA complaints (filed by or against the builder), all Shraddha projects | 14 (11 of 53 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.