Jai Arihant, Ghatkopar East
by Nakoda Infrastructure · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Aug 20233 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 1 yr
- Concrete structure
- 50%Mid-construction
- Booked
- 11 of 7515% · 9 in Jul 2026
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 36
- 2 BHK
- 36
- Other units
- 3
- Total units
- 75
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 50% | 0% | 11 | |
| 100% | 0% | 0% | 9 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400077
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 4 mths | 4 yrs |
| Possession date extended | By 1 yr | 1 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2027 |
| Concrete structure (RCC) | 50% | 98% |
| Units booked | 15% | 84% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Rdk Belvedere, Ghatkopar East
- Sai Twin Tower, Ghatkopar East
- Nav Indralok, Ghatkopar East
- Kevli Plaza – A Wing And Kevli Darshan – B Wing, Ghatkopar East
- Shree Pinal Project, Ghatkopar East
- KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rdk Belvedere | September 2023 | December 2029 | 100% | 14 units booked out of 34 units for sale |
| Sai Twin Tower | September 2023 | December 2027 | 95% | 71 units booked out of 76 units for sale |
| Nav Indralok | June 2023 | December 2026 | 75% | 14 units booked out of 17 units for sale |
| Kevli Plaza – A Wing And Kevli Darshan – B Wing | May 2023 | December 2028 | 63% | 26 units booked out of 67 units for sale |
| Shree Pinal Project | February 2023 | Nov 2027 – Apr 2028 | 100% | 29 units booked out of 34 units for sale |
| KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL | February 2024 | December 2027 | 100% | 90 units booked out of 99 units for sale |
About this project
Jai Arihant by Nakoda Infrastructure is a 75-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in August 2023 with possession due in December 2027. 11 units booked out of total 75 units. The concrete structure (RCC) is 50% complete.
Read full summary
Jai Arihant is a BMC-sanctioned project by Nakoda Infrastructure in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800052413. It was launched in August 2023. It has 75 units in 2 buildings: 72 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 1 year from the original December 2026. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.
11 units booked out of total 75 units (15%). Since the July 2026 update, 2 more units have been booked, the reported concrete structure (RCC) has gone from 0% to 50% and the possession date has moved from December 2026 to December 2027.