Jai Arihant, Ghatkopar East

by Nakoda Infrastructure · Ghatkopar East, Mumbai 400077 · Map

Launched
Aug 20233 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 1 yr
Concrete structure
50%Mid-construction
Booked
11 of 7515% · 9 in Jul 2026
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
36
2 BHK
36
Other units
3
Total units
75
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)50%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 50%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 50%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%11
100%0%0%9
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400077

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400077
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths4 yrs
Possession date extendedBy 1 yr1 of 6
Possession date (MahaRERA)Dec 2027Dec 2027
Concrete structure (RCC)50%98%
Units booked15%84%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Jai Arihant by Nakoda Infrastructure is a 75-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in August 2023 with possession due in December 2027. 11 units booked out of total 75 units. The concrete structure (RCC) is 50% complete.

Read full summary

Jai Arihant is a BMC-sanctioned project by Nakoda Infrastructure in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800052413. It was launched in August 2023. It has 75 units in 2 buildings: 72 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 1 year from the original December 2026. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.

11 units booked out of total 75 units (15%). Since the July 2026 update, 2 more units have been booked, the reported concrete structure (RCC) has gone from 0% to 50% and the possession date has moved from December 2026 to December 2027.