Ambal Parijath Chsl, Chembur
by Rajeshree Enterprises · Chembur, Mumbai 400071 · Map
- Launched
- Jun 20232 yrs 6 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 5 of 956% · 12 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 9 units
Rehab12 units for existing members
Total 21 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 16
- 3 BHK
- 5
- Total units
- 21
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 9
- Rehab units
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 0% | 5 | |
| 100% | 80% | 0% | 5 | |
| 100% | 70% | 0% | 5 | |
| 100% | 70% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400071
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 6 mths | 2 yrs 7 mths |
| Possession date extended | By 1 yr | 4 of 5 |
| Possession date (MahaRERA) | Dec 2026 | Mar 2027 |
| Concrete structure (RCC) | 90% | 100% |
| Units booked (free sale) | 56% | 70% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Arham Aryan, Chembur
- Radha Continental, Chembur
- Vishwa Bhuvan, Chembur
- Heritage Signature, Chembur
- Parsn Bhagyalakshmi, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Arham Aryan | May 2023 | December 2026 | 50% | 11 units booked out of 17 units for sale |
| Radha Continental | February 2023 | October 2027 | 90% | 7 units booked out of 10 units for sale |
| Vishwa Bhuvan | October 2023 | March 2027 | 100% | 6 units booked out of 8 units for sale |
| Heritage Signature | February 2023 | March 2026 | 100% | 3 units booked out of total 11 units |
| Parsn Bhagyalakshmi | October 2023 | May 2027 | 100% | 17 units booked out of 19 units for sale |
About this project
Ambal Parijath Chsl by Rajeshree Enterprises is a 21-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in June 2023 with possession due in December 2026. 5 units booked out of 9 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Ambal Parijath Chsl is a BMC-sanctioned project by Rajeshree Enterprises in Chembur, Mumbai 400071, registered with MahaRERA as P51800051629. It was launched in June 2023. It has 21 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 21 units, 9 are for sale and 12 are rehab units for existing members.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.
5 units booked out of 9 units for sale (56%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 80% to 90%.