Rekhaz, Mulund West
by R Nutan Builders Private Limited · Mulund West, Mumbai 400080 · Map
- Launched
- Mar 20234 yrs promised
- Possession (MahaRERA)
- Mar 2027Not extended
- Concrete structure
- 75%Mid-construction
- Booked (free sale)
- 8 of 1173% · 35 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale8 booked out of 11 units
Rehab35 units for existing members
Total 46 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 8
- 2 BHK
- 16
- 3 BHK
- 22
- Total units
- 46
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 11
- Rehab units
- 35
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 75% | 0% | 8 | |
| 100% | 75% | 0% | – | |
| 100% | 75% | 0% | – | |
| 100% | 75% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400080
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs | 3 yrs 2 mths |
| Possession date extended | No | 3 of 6 |
| Possession date (MahaRERA) | Mar 2027 | Dec 2026 |
| Concrete structure (RCC) | 75% | 100% |
| Units booked (free sale) | 73% | 69% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Pramukh Krupa Phase Two, Mulund West
- Tirupati Apartments Chsl, Mulund West
- Shivram CHSL - Phase 3, Mulund West
- Aishwarya Optima, Mulund West
- Shubh Parshwa Heights Phase I, Mulund West
- Sunset Gardens by Marathon, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Pramukh Krupa Phase Two | April 2023 | March 2027 | 100% | 49 units booked out of 71 units for sale |
| Tirupati Apartments Chsl | January 2023 | October 2026 | 100% | 16 units booked out of 20 units for sale |
| Shivram CHSL - Phase 3 | January 2023 | December 2025 | 100% | 19 units booked out of total 48 units |
| Aishwarya Optima | May 2023 | April 2027 | 100% | 9 units booked out of 49 units for sale |
| Shubh Parshwa Heights Phase I | July 2023 | December 2026 | 0% | – |
| Sunset Gardens by Marathon | October 2022 | December 2026 | 33% | 70 units booked out of total 87 units |
About this project
Rekhaz by R Nutan Builders Private Limited is a 46-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in March 2023 with possession due in March 2027. 8 units booked out of 11 units for sale. The concrete structure (RCC) is 75% complete.
Read full summary
Rekhaz is a BMC-sanctioned project by R Nutan Builders Private Limited in Mulund West, Mumbai 400080, registered with MahaRERA as P51800049987. It was launched in March 2023. It has 46 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 46 units, 11 are for sale and 35 are rehab units for existing members.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started.
8 units booked out of 11 units for sale (73%).