Pramukh Krupa Phase Two, Mulund West

by Pinal Realty LLP · Mulund West, Mumbai 400080 · Map

Launched
Apr 20233 yrs 11 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
49 of 7169% · 25 rehab units
Buildings
10.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale49 booked out of 71 units

Rehab25 units for existing members

Land-owner share1 unit, not for sale

Total 97 units. Rehab and land-owner units are not for sale.

Project facts

1 RK
14
1 BHK
28
2 BHK
23
3 BHK
32
Total units
97
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
1
Free-sale units
71
Rehab units
25
Land-owner share (not for sale)
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 45%Dec 2025: Concrete structure (RCC) 60%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 100%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%30%49
100%60%0%–
100%60%0%–
100%45%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 11 mths4 yrs 4 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Mar 2027Jun 2027
Concrete structure (RCC)100%80%
Units booked (free sale)69%31%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Pramukh Krupa Phase Two by Pinal Realty LLP is a 97-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in April 2023 with possession due in March 2027. 49 units booked out of 71 units for sale. The concrete structure (RCC) is complete.

Read full summary

Pramukh Krupa Phase Two is an SRA-sanctioned project by Pinal Realty LLP in Mulund West, Mumbai 400080, registered with MahaRERA as P51800050490. It was launched in April 2023. It has 97 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 97 units, 71 are for sale, 25 are rehab units for existing members and 1 is the land-owner's share, not for sale.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.

49 units booked out of 71 units for sale (69%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 60% to 100%.