Tirupati Apartments Chsl, Mulund West
Lapsed
by Tirupati Aparmtnets Co Operative Housing Society Limited · Mulund West, Mumbai 400080 · Map
- Launched
- Jan 20232 yrs 9 mths originally promised
- Possession (MahaRERA)
- Oct 2026Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 16 of 2080% · 28 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale16 booked out of 20 units
Rehab28 units for existing members
Total 48 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 25
- 3 BHK
- 16
- 4 BHK
- 4
- 5+ BHK
- 3
- Total units
- 48
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 20
- Rehab units
- 28
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 10% | 16 | |
| 100% | 100% | 10% | 34 | |
| 100% | 100% | 10% | 34 | |
| 100% | 90% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400080
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 3 yrs 10 mths |
| Possession date extended | By 1 yr | 2 of 6 |
| Possession date (MahaRERA) | Oct 2026 | Jan 2027 |
| Concrete structure (RCC) | 100% | 80% |
| Units booked (free sale) | 80% | 73% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Shivram CHSL - Phase 3, Mulund West
- The New Anand Deep Chs Ltd, Mulund West
- Austin Heights, Mulund West
- Rekhaz, Mulund West
- Shree Siidha Pride, Mulund West
- Kusum Classic of Pulivahana CHS Ltd, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shivram CHSL - Phase 3 | January 2023 | December 2025 | 100% | 19 units booked out of total 48 units |
| The New Anand Deep Chs Ltd | December 2022 | September 2026 | 95% | 28 units booked out of 28 units for sale |
| Austin Heights | December 2022 | October 2029 | 0% | – |
| Rekhaz | March 2023 | March 2027 | 75% | 8 units booked out of 11 units for sale |
| Shree Siidha Pride | November 2022 | December 2027 | 0% | 22 units booked out of 28 units for sale |
| Kusum Classic of Pulivahana CHS Ltd | November 2022 | December 2026 | 85% | 2 units booked out of 17 units for sale |
About this project
Tirupati Apartments Chsl by Tirupati Aparmtnets Co Operative Housing Society Limited is a 48-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in January 2023; its MahaRERA registration has lapsed. 16 units booked out of 20 units for sale. The concrete structure (RCC) is complete.
Read full summary
Tirupati Apartments Chsl is a BMC-sanctioned project by Tirupati Aparmtnets Co Operative Housing Society Limited in Mulund West, Mumbai 400080, registered with MahaRERA as P51800048581. It was launched in January 2023. It has 48 units in 1 building, with 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 48 units, 20 are for sale and 28 are rehab units for existing members.
Its registered possession date is October 2026, extended by 1 year from the original October 2025. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.
16 units booked out of 20 units for sale (80%).