Saraswati Paradise, Mulund West

by Metro Dwellers Private Limited · Mulund West, Mumbai 400080 · Map

Launched
Jun 20234 yrs 6 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
156 of 17987% · 56 rehab units
Buildings
20.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale156 booked out of 179 units

Rehab56 units for existing members

Total 235 units. Rehab units are not for sale.

Project facts

1 RK
33
1 BHK
59
2 BHK
86
3 BHK
1
Other units
56
Total units
235
Buildings
2
Land
0.8 acres
Phases
1
MahaRERA complaints
0
Free-sale units
179
Rehab units
56
Reserved units
86

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 50%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 35%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 100%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%30%156
50%35%0%151
0%0%0%152
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 80–400 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 6 mths4 yrs 2 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2027Sep 2027
Concrete structure (RCC)100%67%
Units booked (free sale)87%33%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Saraswati Paradise by Metro Dwellers Private Limited is a 235-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in June 2023 with possession due in December 2027. 156 units booked out of 179 units for sale. The concrete structure (RCC) is complete.

Read full summary

Saraswati Paradise is an SRA-sanctioned project by Metro Dwellers Private Limited in Mulund West, Mumbai 400080, registered with MahaRERA as P51800051636. It was launched in June 2023. It has 235 units in 2 buildings: 179 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 56 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 235 units, 179 are for sale and 56 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.

156 units booked out of 179 units for sale (87%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 35% to 100%.