Saraswati Paradise, Mulund West
by Metro Dwellers Private Limited · Mulund West, Mumbai 400080 · Map
- Launched
- Jun 20234 yrs 6 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 156 of 17987% · 56 rehab units
- Buildings
- 20.8 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale156 booked out of 179 units
Rehab56 units for existing members
Total 235 units. Rehab units are not for sale.
Project facts
- 1 RK
- 33
- 1 BHK
- 59
- 2 BHK
- 86
- 3 BHK
- 1
- Other units
- 56
- Total units
- 235
- Buildings
- 2
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 179
- Rehab units
- 56
- Reserved units
- 86
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 30% | 156 | |
| 50% | 35% | 0% | 151 | |
| 0% | 0% | 0% | 152 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400080
Projects with 80–400 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 6 mths | 4 yrs 2 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Sep 2027 |
| Concrete structure (RCC) | 100% | 67% |
| Units booked (free sale) | 87% | 33% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Saraswati Square, Mulund West
- Arkade Nest, Mulund West
- Green Origin, Mulund West
- Pramukh Krupa Phase Two, Mulund West
- Dhanraj Tower, Mulund West
- Shraddha Panorama, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Saraswati Square | May 2023 | December 2027 | 85% | 51 units booked out of 117 units for sale |
| Arkade Nest | May 2023 | June 2027 | 79% | 268 units booked out of total 351 units |
| Green Origin | August 2023 | August 2029 | 10% | 34 units booked out of total 153 units |
| Pramukh Krupa Phase Two | April 2023 | March 2027 | 100% | 49 units booked out of 71 units for sale |
| Dhanraj Tower | March 2023 | June 2027 | 55% | 18 units booked out of 110 units for sale |
| Shraddha Panorama | October 2023 | December 2027 | 30% | 40 units booked out of 182 units for sale |
About this project
Saraswati Paradise by Metro Dwellers Private Limited is a 235-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in June 2023 with possession due in December 2027. 156 units booked out of 179 units for sale. The concrete structure (RCC) is complete.
Read full summary
Saraswati Paradise is an SRA-sanctioned project by Metro Dwellers Private Limited in Mulund West, Mumbai 400080, registered with MahaRERA as P51800051636. It was launched in June 2023. It has 235 units in 2 buildings: 179 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 56 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 235 units, 179 are for sale and 56 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.
156 units booked out of 179 units for sale (87%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 35% to 100%.