Unique Shine, Vikhroli

by Fazal Mehmood Shaikh · Vikhroli, Mumbai 400083 · Map

Launched
May 20233 yrs 7 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
87%Mid-construction
Booked
77 of 11766%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
76
2 BHK
38
Other units
3
Total units
117
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)87%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 87%Dec 2025: Concrete structure (RCC) 87%Jul 2026: Concrete structure (RCC) 87%Oct 2026: Concrete structure (RCC) 87%Dec 2024: Final finishes 20%Dec 2025: Final finishes 20%Jul 2026: Final finishes 20%Oct 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 87%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%87%20%77
100%87%20%–
100%87%20%–
100%87%20%77

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400083

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400083
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 7 mths3 yrs 8 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2026Dec 2026
Concrete structure (RCC)87%100%
Units booked66%64%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Unique Shine by Fazal Mehmood Shaikh is a 117-unit project in Vikhroli, Mumbai 400083, launched in May 2023 with possession due in December 2026. 77 units booked out of total 117 units. The concrete structure (RCC) is 87% complete.

Read full summary

Unique Shine is a project by Fazal Mehmood Shaikh in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800050757. It was launched in May 2023. It has 117 units in 1 building: 114 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 87% complete, final finishes 20% complete.

77 units booked out of total 117 units (66%).