Sagar Sangeet Chs Adityaraj Paradise, Vikhroli
by Adityaraj Housing Developers · Vikhroli, Mumbai 400083 · Map
- Launched
- Jun 20233 yrs 6 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- 65 of 13050%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 70
- 3 BHK
- 40
- Other units
- 20
- Total units
- 130
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 65% | 65 | |
| 100% | 100% | 40% | – | |
| 100% | 8% | 0% | – | |
| 100% | 8% | 0% | 65 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400083
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 6 mths | 3 yrs 6 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2026 |
| Concrete structure (RCC) | 100% | 74% |
| Units booked | 50% | 64% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Unique Enclave Residency, Vikhroli
- Unique Shine, Vikhroli
- Unique Prestige, Vikhroli
- Swastik Coral, Vikhroli
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Unique Enclave Residency | June 2023 | September 2026 | 21% | 43 units booked out of total 118 units |
| Unique Shine | May 2023 | December 2026 | 87% | 77 units booked out of total 117 units |
| Unique Prestige | July 2023 | December 2026 | 62% | 103 units booked out of total 153 units |
| Swastik Coral | March 2023 | December 2027 | 100% | 75 units booked out of total 121 units |
About this project
Sagar Sangeet Chs Adityaraj Paradise by Adityaraj Housing Developers is a 130-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in June 2023 with possession due in December 2026. 65 units booked out of total 130 units. The concrete structure (RCC) is complete.
Read full summary
Sagar Sangeet Chs Adityaraj Paradise is a MHADA-sanctioned project by Adityaraj Housing Developers in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800051660. It was launched in June 2023. It has 130 units in 1 building: 110 homes (2 and 3 BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 65% complete.
65 units booked out of total 130 units (50%).
Adityaraj's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 29 |
|---|---|
| Total units across these projects | 3,149 |
| Completed without extending the possession date | 7 |
| Completed after an extension | 2 |
| Lapsed | 10 |
| Under construction | 10 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 3 years 6 months |
| MahaRERA complaints (filed by or against the builder), all Adityaraj projects | 2 (2 of 29 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.