Skip to main content

Roopniketan Co.Operative Housing Society Ltd, Mulund East

Lapsed

by Shree Shingar Constructions Private Limited · Mulund East, Mumbai 400081 · Map

Launched
Jun 20232 yrs 6 mths originally promised
Possession (MahaRERA)
Jun 2026Extended by 6 mthsWhat does Lapsed mean?
Concrete structure
95%Mid-construction
Booked (free sale)
35 of 4971% · 31 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale35 booked out of 49 units

Rehab31 units for existing members

Total 80 units. Rehab units are not for sale.

Project facts

1 BHK
19
2 BHK
41
3 BHK
20
Total units
80
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
49
Rehab units
31
Reserved units
7

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)95%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 16%Dec 2025: Concrete structure (RCC) 95%Jul 2026: Concrete structure (RCC) 95%Oct 2026: Concrete structure (RCC) 95%Dec 2024: Final finishes 0%Dec 2025: Final finishes 50%Jul 2026: Final finishes 55%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 95%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%90%35
100%95%55%32
100%95%50%19
100%16%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400081

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400081
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 6 mths3 yrs 4 mths
Possession date extendedBy 6 mths1 of 5
Possession date (MahaRERA)Jun 2026Dec 2026
Concrete structure (RCC)95%95%
Units booked (free sale)71%47%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Roopniketan Co.Operative Housing Society Ltd by Shree Shingar Constructions Private Limited is an 80-unit BMC-sanctioned project in Mulund East, Mumbai 400081, launched in June 2023; its MahaRERA registration has lapsed. 35 units booked out of 49 units for sale. The concrete structure (RCC) is 95% complete.

Read full summary

Roopniketan Co.Operative Housing Society Ltd is a BMC-sanctioned project by Shree Shingar Constructions Private Limited in Mulund East, Mumbai 400081, registered with MahaRERA as P51800051469. It was launched in June 2023. It has 80 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 80 units, 49 are for sale and 31 are rehab units for existing members.

Possession was due in June 2026, after an extension of 6 months from the original December 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 95% complete, final finishes 90% complete.

35 units booked out of 49 units for sale (71%). Since the July 2026 update, 3 more units have been booked.