Skip to main content

Mithagar Road Ekta CHSL, Mulund East

Ready to move

by Palan Realty Private Limited · Mulund East, Mumbai 400081 · Map

Launched
Sep 20232 yrs 3 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
100%Ready to move
Booked (free sale)
20 of 4842% · 28 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale20 booked out of 48 units

Rehab28 units for existing members

Total 76 units. Rehab units are not for sale.

Project facts

2 BHK
76
Total units
76
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
48
Rehab units
28

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 30%Jul 2026: Final finishes 60%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%20
100%100%60%16
100%100%30%12
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400081

Projects with 30–200 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400081
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 3 mths2 yrs 10 mths
Possession date extendedBy 1 yr2 of 5
Possession date (MahaRERA)Dec 2026Dec 2026
Concrete structure (RCC)100%96%
Units booked (free sale)42%55%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Mithagar Road Ekta CHSL by Palan Realty Private Limited is a 76-unit MHADA-sanctioned project in Mulund East, Mumbai 400081, launched in September 2023 with possession due in December 2026. 20 units booked out of 48 units for sale. The concrete structure (RCC) is complete.

Read full summary

Mithagar Road Ekta CHSL is a MHADA-sanctioned project by Palan Realty Private Limited in Mulund East, Mumbai 400081, registered with MahaRERA as P51800052661. It was launched in September 2023. It has 76 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 76 units, 48 are for sale and 28 are rehab units for existing members.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

20 units booked out of 48 units for sale (42%). Since the July 2026 update, 4 more units have been booked.