Bank Of India Employees Sukhada Chsl, Borivali West
Ready to move
by M/S Hirani Realtors · Borivali West, Mumbai 400091 · Map
- Launched
- Jul 20232 yrs 11 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 6 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 27 of 3382% · 45 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale27 booked out of 33 units
Rehab45 units for existing members
Total 78 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 36
- 3 BHK
- 33
- 4 BHK
- 1
- Other units
- 8
- Total units
- 78
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 33
- Rehab units
- 45
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 27 | |
| 100% | 100% | 0% | 19 | |
| 100% | 100% | 0% | 13 | |
| 100% | 84% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400091
Projects with 30–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 11 mths | 2 yrs 8 mths |
| Possession date extended | By 6 mths | 1 of 3 |
| Possession date (MahaRERA) | Dec 2026 | May 2027 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 82% | 82% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Rashmi Square, Borivali West
- Gagansagar, Borivali West
- Avyukta Vedant, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rashmi Square | February 2024 | May 2027 | 100% | 62 units booked out of 74 units for sale |
| Gagansagar | April 2024 | December 2026 | 100% | 44 units booked out of 56 units for sale |
| Avyukta Vedant | June 2024 | March 2029 | 95% | 65 units booked out of 79 units for sale |
About this project
Bank Of India Employees Sukhada Chsl by M/S Hirani Realtors is a 78-unit BMC-sanctioned project in Borivali West, Mumbai 400091, launched in July 2023 with possession due in December 2026. 27 units booked out of 33 units for sale. The concrete structure (RCC) is complete.
Read full summary
Bank Of India Employees Sukhada Chsl is a BMC-sanctioned project by M/S Hirani Realtors in Borivali West, Mumbai 400091, registered with MahaRERA as P51800051922. It was launched in July 2023. It has 78 units in 1 building: 70 homes (2, 3 and 4 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 78 units, 33 are for sale and 45 are rehab units for existing members.
Its registered possession date is December 2026, extended by 6 months from the original June 2026. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
27 units booked out of 33 units for sale (82%). Since the July 2026 update, 8 more units have been booked.