Skip to main content

Gagansagar, Borivali West

by Hum Developers Private Limited · Borivali West, Mumbai 400091 · Map

Launched
Apr 20242 yrs 8 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
44 of 5679% · 36 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale44 booked out of 56 units

Rehab36 units for existing members

Total 92 units. Rehab units are not for sale.

Project facts

1 RK
16
1 BHK
10
2 BHK
30
3 BHK
36
Total units
92
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
56
Rehab units
36
Reserved units
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 5%Dec 2025: Concrete structure (RCC) 67%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%44
100%100%0%36
100%67%0%29
100%5%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400091

Projects with 40–200 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400091
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 8 mths3 yrs 10 mths
Possession date extendedNo2 of 4
Possession date (MahaRERA)Dec 2026Apr 2028
Concrete structure (RCC)100%100%
Units booked (free sale)79%82%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Gagansagar by Hum Developers Private Limited is a 92-unit BMC-sanctioned project in Borivali West, Mumbai 400091, launched in April 2024 with possession due in December 2026. 44 units booked out of 56 units for sale. The concrete structure (RCC) is complete.

Read full summary

Gagansagar is a BMC-sanctioned project by Hum Developers Private Limited in Borivali West, Mumbai 400091, registered with MahaRERA as P51800055645. It was launched in April 2024. It has 92 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 92 units, 56 are for sale and 36 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

44 units booked out of 56 units for sale (79%). Since the July 2026 update, 8 more units have been booked.