Rashmi Square, Borivali West
Ready to move
by Modi's Navnirman Limited · Borivali West, Mumbai 400091 · Map
- Launched
- Feb 20242 yrs 3 mths originally promised
- Possession (MahaRERA)
- May 2027Extended by 1 yr
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 62 of 7484% · 68 rehab units
- Buildings
- 20.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale62 booked out of 74 units
Rehab68 units for existing members
Total 142 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 33
- 2 BHK
- 80
- 3 BHK
- 15
- 4 BHK
- 2
- Other units
- 12
- Total units
- 142
- Buildings
- 2
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 74
- Rehab units
- 68
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 62 | |
| 100% | 90% | 75% | 7 | |
| 100% | 68% | 68% | 4 | |
| 100% | 33% | 25% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400091
Projects with 60–300 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 3 mths | 4 yrs 8 mths |
| Possession date extended | By 1 yr | 1 of 5 |
| Possession date (MahaRERA) | May 2027 | Mar 2029 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 84% | 79% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Gagansagar, Borivali West
- Avyukta Vedant, Borivali West
- Sheetal, Borivali West
- Bank Of India Employees Sukhada Chsl, Borivali West
- Sheetal Shashanka, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Gagansagar | April 2024 | December 2026 | 100% | 44 units booked out of 56 units for sale |
| Avyukta Vedant | June 2024 | March 2029 | 95% | 65 units booked out of 79 units for sale |
| Sheetal | July 2024 | March 2029 | 100% | 22 units booked out of 35 units for sale |
| Bank Of India Employees Sukhada Chsl | July 2023 | December 2026 | 100% | 27 units booked out of 33 units for sale |
| Sheetal Shashanka | December 2024 | December 2029 | 95% | 106 units booked out of 191 units for sale |
About this project
Rashmi Square by Modi's Navnirman Limited is a 142-unit BMC-sanctioned project in Borivali West, Mumbai 400091, launched in February 2024 with possession due in May 2027. 62 units booked out of 74 units for sale. The concrete structure (RCC) is complete.
Read full summary
Rashmi Square is a BMC-sanctioned project by Modi's Navnirman Limited in Borivali West, Mumbai 400091, registered with MahaRERA as P51800054722. It was launched in February 2024. It has 142 units in 2 buildings: 130 homes (1, 2, 3 and 4 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 142 units, 74 are for sale and 68 are rehab units for existing members.
Its registered possession date is May 2027, extended by 1 year from the original May 2026. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
62 units booked out of 74 units for sale (84%). Since the July 2026 update, 55 more units have been booked and the reported concrete structure (RCC) has gone from 90% to 100%.