Isha Vasyam, Bhandup East

Ready to move

by Jyoti Sagar Corporation · Bhandup East, Mumbai 400042 · Map

Launched
Jul 20233 yrs 11 mths promised
Possession (MahaRERA)
Jun 2027Not extended
Concrete structure
100%Ready to move
Booked (free sale)
10 of 1759%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale10 booked out of 17 units

Land-owner share7 units, not for sale

Total 24 units. Land-owner units are not for sale.

Project facts

1 BHK
13
2 BHK
10
Other units
1
Total units
24
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
17
Land-owner share (not for sale)
7

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 40%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%10
100%100%90%10
100%100%90%10
100%100%40%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400042

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400042
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 11 mths3 yrs 6 mths
Possession date extendedNo2 of 4
Possession date (MahaRERA)Jun 2027Oct 2027
Concrete structure (RCC)100%95%
Units booked (free sale)59%57%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Isha Vasyam by Jyoti Sagar Corporation is a 24-unit BMC-sanctioned project in Bhandup East, Mumbai 400042, launched in July 2023 with possession due in June 2027. 10 units booked out of 17 units for sale. The concrete structure (RCC) is complete.

Read full summary

Isha Vasyam is a BMC-sanctioned project by Jyoti Sagar Corporation in Bhandup East, Mumbai 400042, registered with MahaRERA as P51800051969. It was launched in July 2023. It has 24 units in 1 building: 23 homes (1 and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 24 units, 17 are for sale and 7 are the land-owner's share, not for sale.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

10 units booked out of 17 units for sale (59%).