Ramchandra Enclave, Bhandup East
Ready to move
by Mango Village Private Limited · Bhandup East, Mumbai 400042 · Map
- Launched
- Sep 20233 yrs 10 mths promised
- Possession (MahaRERA)
- Jul 2027Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 7 of 1450%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale7 booked out of 14 units
Land-owner share4 units, not for sale
Total 18 units. Land-owner units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 3
- 2 BHK
- 11
- 3 BHK
- 3
- Total units
- 18
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 14
- Land-owner share (not for sale)
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 7 | |
| 100% | 100% | 0% | 7 | |
| 100% | 100% | 0% | 5 | |
| 100% | 80% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400042
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 10 mths | 3 yrs 7 mths |
| Possession date extended | No | 2 of 4 |
| Possession date (MahaRERA) | Jul 2027 | Sep 2027 |
| Concrete structure (RCC) | 100% | 95% |
| Units booked (free sale) | 50% | 62% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Bhumi Akshay, Bhandup East
- Isha Vasyam, Bhandup East
- Shivmangal Residency, Bhandup East
- Rajshree Ashish Co-Operative Housing Society Limited, Bhandup East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bhumi Akshay | July 2023 | June 2028 | 35% | 11 units booked out of total 17 units |
| Isha Vasyam | July 2023 | June 2027 | 100% | 10 units booked out of 17 units for sale |
| Shivmangal Residency | June 2023 | August 2026 | 100% | 5 units booked out of 14 units for sale |
| Rajshree Ashish Co-Operative Housing Society Limited | March 2023 | January 2028 | 90% | 13 units booked out of 14 units for sale |
About this project
Ramchandra Enclave by Mango Village Private Limited is an 18-unit BMC-sanctioned project in Bhandup East, Mumbai 400042, launched in September 2023 with possession due in July 2027. 7 units booked out of 14 units for sale. The concrete structure (RCC) is complete.
Read full summary
Ramchandra Enclave is a BMC-sanctioned project by Mango Village Private Limited in Bhandup East, Mumbai 400042, registered with MahaRERA as P51800052595. It was launched in September 2023. It has 18 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 18 units, 14 are for sale and 4 are the land-owner's share, not for sale.
Its registered possession date is July 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
7 units booked out of 14 units for sale (50%).