Shraddha Palacious, Bhandup West
by Shraddha Prime Projects Limited · Bhandup West, Mumbai 400078 · Map
- Launched
- Aug 20234 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 94%Mid-construction
- Booked (free sale)
- 181 of 26768%
- Buildings
- 21.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale181 booked out of 267 units
Land-owner share131 units, not for sale
Total 398 units. Land-owner units are not for sale.
Project facts
- 1 RK
- 2
- 1 BHK
- 255
- 2 BHK
- 137
- Other units
- 4
- Total units
- 398
- Buildings
- 2
- Land
- 1.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 267
- Land-owner share (not for sale)
- 131
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 94% | 38% | 181 | |
| 100% | 85% | 38% | 181 | |
| 100% | 50% | 0% | 181 | |
| 100% | 3% | 0% | 145 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400078
Projects with 150–800 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 4 mths | 5 yrs 6 mths |
| Possession date extended | No | 1 of 3 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2028 |
| Concrete structure (RCC) | 94% | 80% |
| Units booked (free sale) | 68% | 67% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Marshal Srishti III, Bhandup West
- Sugee Vaayu, Bhandup West
- Sky 27, Bhandup West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Marshal Srishti III | June 2023 | December 2028 | 100% | 121 units booked out of 124 units for sale |
| Sugee Vaayu | December 2023 | April 2032 | 0% | 0 units booked out of total 546 units |
| Sky 27 | January 2024 | December 2028 | 80% | 142 units booked out of total 212 units |
About this project
Shraddha Palacious by Shraddha Prime Projects Limited is a 398-unit SRA-sanctioned project in Bhandup West, Mumbai 400078, launched in August 2023 with possession due in December 2027. 181 units booked out of 267 units for sale. The concrete structure (RCC) is 94% complete.
Read full summary
Shraddha Palacious is an SRA-sanctioned project by Shraddha Prime Projects Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800052241. It was launched in August 2023. It has 398 units in 2 buildings: 394 homes (1 RK, 1 BHK and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 398 units, 267 are for sale and 131 are the land-owner's share, not for sale.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 94% complete, final finishes 38% complete.
181 units booked out of 267 units for sale (68%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 85% to 94%.
Shraddha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 53 |
|---|---|
| Total units across these projects | 9,707 |
| Completed without extending the possession date | 16 |
| Completed after an extension | 4 |
| Lapsed | 5 |
| Under construction | 28 |
| Possession date extended on the builder's application | 18 |
| Typical time from launch to 100% structure | 4 years |
| MahaRERA complaints (filed by or against the builder), all Shraddha projects | 14 (11 of 53 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.