Sky 27, Bhandup West

by Space Developers · Bhandup West, Mumbai 400078 · Map

Launched
Jan 20244 yrs 11 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
80%Mid-construction
Booked
142 of 21267% · 112 in Jul 2026
Buildings
11.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
2
1 BHK
134
2 BHK
76
Total units
212
Buildings
1
Land
1.2 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 5%Jul 2026: Concrete structure (RCC) 15%Oct 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 80%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%0%142
100%15%0%112
100%5%0%–
100%0%0%18

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400078

Projects with 100–450 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 11 mths4 yrs 10 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2028Dec 2028
Concrete structure (RCC)80%80%
Units booked67%8%
MahaRERA complaints (filed by or against the builder)10

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Sky 27 by Space Developers is a 212-unit SRA-sanctioned project in Bhandup West, Mumbai 400078, launched in January 2024 with possession due in December 2028. 142 units booked out of total 212 units. The concrete structure (RCC) is 80% complete.

Read full summary

Sky 27 is an SRA-sanctioned project by Space Developers in Bhandup West, Mumbai 400078, registered with MahaRERA as P51900054576. It was launched in January 2024. It has 212 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.

142 units booked out of total 212 units (67%). Since the July 2026 update, 30 more units have been booked and the reported concrete structure (RCC) has gone from 15% to 80%.