Malad Amar Co-Operative Housing Society Ltd, Malad East

by Ardhya Universal LLP · Malad East, Mumbai 400097 · Map

Launched
Aug 20231 yr 9 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 1 yr 11 mths
Concrete structure
90%Mid-construction
Booked (free sale)
10 of 1377% · 13 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale10 booked out of 13 units

Rehab13 units for existing members

Total 26 units. Rehab units are not for sale.

Project facts

1 BHK
15
2 BHK
9
Other units
2
Total units
26
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
13
Rehab units
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 0%Dec 2025: Final finishes 10%Jul 2026: Final finishes 50%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 90%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%50%10
100%90%50%10
100%80%10%6
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400097

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 9 mths2 yrs 2 mths
Possession date extendedBy 1 yr 11 mths4 of 4
Possession date (MahaRERA)Apr 2027Jul 2026
Concrete structure (RCC)90%100%
Units booked (free sale)77%81%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Malad Amar Co-Operative Housing Society Ltd by Ardhya Universal LLP is a 26-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in August 2023 with possession due in April 2027. 10 units booked out of 13 units for sale. The concrete structure (RCC) is 90% complete.

Read full summary

Malad Amar Co-Operative Housing Society Ltd is a BMC-sanctioned project by Ardhya Universal LLP in Malad East, Mumbai 400097, registered with MahaRERA as P51800052335. It was launched in August 2023. It has 26 units in 1 building: 24 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 26 units, 13 are for sale and 13 are rehab units for existing members.

Its registered possession date is April 2027, extended by 1 year 11 months from the original May 2025. Construction: excavation complete, structure (RCC) 90% complete, final finishes 50% complete.

10 units booked out of 13 units for sale (77%). Since the July 2026 update, the possession date has moved from March 2026 to April 2027.