Ashiyana Apartment CHSL Ltd, Malad East
by Pearl Infra · Malad East, Mumbai 400097 · Map
- Launched
- Jan 20242 yrs 8 mths originally promised
- Possession (MahaRERA)
- Sep 2027Extended by 1 yr
- Concrete structure
- 70%Mid-construction
- Booked (free sale)
- 1 of 119% · 17 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 11 units
Rehab17 units for existing members
Total 28 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 1
- 2 BHK
- 25
- 3 BHK
- 1
- Total units
- 28
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 11
- Rehab units
- 17
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 0% | 1 | |
| 100% | 24% | 0% | 1 | |
| 100% | 8% | 0% | 1 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400097
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 8 mths | 2 yrs 10 mths |
| Possession date extended | By 1 yr | 2 of 6 |
| Possession date (MahaRERA) | Sep 2027 | May 2027 |
| Concrete structure (RCC) | 70% | 100% |
| Units booked (free sale) | 9% | 79% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Rajhans Solitaire, Malad East
- Nikitara, Malad East
- Harshail Emerald Apartment, Malad East
- Malad Amar Co-Operative Housing Society Ltd, Malad East
- Ghanwat Accord, Malad East
- Sheetal Hira, Malad East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rajhans Solitaire | November 2023 | August 2026 | 100% | 17 units booked out of 21 units for sale |
| Nikitara | April 2024 | September 2029 | 100% | 21 units booked out of 45 units for sale |
| Harshail Emerald Apartment | May 2024 | January 2027 | 100% | 2 units booked out of total 14 units |
| Malad Amar Co-Operative Housing Society Ltd | August 2023 | April 2027 | 90% | 10 units booked out of 13 units for sale |
| Ghanwat Accord | June 2024 | December 2027 | 90% | 50 units booked out of 59 units for sale |
| Sheetal Hira | July 2024 | June 2027 | 100% | 28 units booked out of 28 units for sale |
About this project
Ashiyana Apartment CHSL Ltd by Pearl Infra is a 28-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in January 2024 with possession due in September 2027. 1 unit booked out of 11 units for sale. The concrete structure (RCC) is 70% complete.
Read full summary
Ashiyana Apartment CHSL Ltd is a BMC-sanctioned project by Pearl Infra in Malad East, Mumbai 400097, registered with MahaRERA as P51800054430. It was launched in January 2024. It has 28 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 28 units, 11 are for sale and 17 are rehab units for existing members.
Its registered possession date is September 2027, extended by 1 year from the original September 2026. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.
1 unit booked out of 11 units for sale (9%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 24% to 70%.