Rdk Belvedere, Ghatkopar East

by Rdk Constructions · Ghatkopar East, Mumbai 400077 · Map

Launched
Sep 20236 yrs 3 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
14 of 3441% · 30 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale14 booked out of 34 units

Rehab30 units for existing members

Total 64 units. Rehab units are not for sale.

Project facts

1 BHK
9
2 BHK
50
Other units
5
Total units
64
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
34
Rehab units
30
Reserved units
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 59%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 25%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%14
100%100%25%14
100%100%0%14
100%59%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400077

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400077
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 3 mths4 yrs 1 mth
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2029Dec 2027
Concrete structure (RCC)100%82%
Units booked (free sale)41%65%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Rdk Belvedere by Rdk Constructions is a 64-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in September 2023 with possession due in December 2029. 14 units booked out of 34 units for sale. The concrete structure (RCC) is complete.

Read full summary

Rdk Belvedere is a BMC-sanctioned project by Rdk Constructions in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800052507. It was launched in September 2023. It has 64 units in 1 building: 59 homes (1 and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 64 units, 34 are for sale and 30 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.

14 units booked out of 34 units for sale (41%).