- Launched
- Aug 20234 yrs 8 mths promised
- Possession (MahaRERA)
- Apr 2028Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 120 of 14086% · 90 rehab units
- Buildings
- 51.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale120 booked out of 140 units
Rehab90 units for existing members
Total 230 units. Rehab units are not for sale.
Project facts
- 1 RK
- 2
- 1 BHK
- 11
- 2 BHK
- 54
- 3 BHK
- 156
- Other units
- 7
- Total units
- 230
- Buildings
- 5
- Land
- 1.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 140
- Rehab units
- 90
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 120 | |
| 100% | 100% | 65% | 117 | |
| 85% | 0% | 0% | – | |
| 85% | 0% | 0% | 59 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400069
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 8 mths | 3 yrs 8 mths |
| Possession date extended | No | 1 of 3 |
| Possession date (MahaRERA) | Apr 2028 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 86% | 51% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Nicco Residency, Andheri East
- Parleshwar Aangan, Andheri East
- Veena Synergy, Andheri East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Nicco Residency | April 2023 | December 2026 | 38% | 100 units booked out of total 275 units |
| Parleshwar Aangan | February 2023 | December 2026 | 100% | 63 units booked out of 124 units for sale |
| Veena Synergy | February 2023 | December 2026 | 100% | 171 units booked out of total 171 units |
About this project
Atharv Aaradhyam by Atharv Infra LLP is a 230-unit BMC-sanctioned project in Andheri East, Mumbai 400069, launched in August 2023 with possession due in April 2028. 120 units booked out of 140 units for sale. The concrete structure (RCC) is complete.
Read full summary
Atharv Aaradhyam is a BMC-sanctioned project by Atharv Infra LLP in Andheri East, Mumbai 400069, registered with MahaRERA as P51800052443. It was launched in August 2023. It has 230 units in 5 buildings: 223 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 230 units, 140 are for sale and 90 are rehab units for existing members.
Its registered possession date is April 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
120 units booked out of 140 units for sale (86%). Since the July 2026 update, 3 more units have been booked.