Parleshwar Aangan, Andheri East

Ready to move

by Panom Developers LLP · Andheri East, Mumbai 400069 · Map

Launched
Feb 20232 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
100%Ready to move
Booked (free sale)
63 of 12451% · 116 rehab units
Buildings
32.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale63 booked out of 124 units

Rehab116 units for existing members

Total 240 units. Rehab units are not for sale.

Project facts

1 BHK
154
2 BHK
62
3 BHK
10
4 BHK
1
Other units
13
Total units
240
Buildings
3
Land
2.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
124
Rehab units
116

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%63
100%100%100%49
100%0%0%24
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400069

Projects with 100–500 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400069
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths3 yrs 7 mths
Possession date extendedBy 1 yr2 of 6
Possession date (MahaRERA)Dec 2026Dec 2026
Concrete structure (RCC)100%92%
Units booked (free sale)51%66%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Parleshwar Aangan by Panom Developers LLP is a 240-unit SRA-sanctioned project in Andheri East, Mumbai 400069, launched in February 2023 with possession due in December 2026. 63 units booked out of 124 units for sale. The concrete structure (RCC) is complete.

Read full summary

Parleshwar Aangan is an SRA-sanctioned project by Panom Developers LLP in Andheri East, Mumbai 400069, registered with MahaRERA as P51800049682. It was launched in February 2023. It has 240 units in 3 buildings: 227 homes (1, 2, 3 and 4 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 240 units, 124 are for sale and 116 are rehab units for existing members.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

63 units booked out of 124 units for sale (51%). Since the July 2026 update, 14 more units have been booked.