Nicco Residency, Andheri East

by Neelkamal Realty & Construction LLP · Andheri East, Mumbai 400069 · Map

Launched
Apr 20233 yrs 8 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
38%Mid-construction
Booked
100 of 27536%
Buildings
41.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
165
3 BHK
65
4 BHK
21
Other units
23
Total units
275
Buildings
4
Land
1.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation75%
Concrete structure (slabs)38%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 75%Dec 2025: Excavation 75%Jul 2026: Excavation 75%Oct 2026: Excavation 75%Dec 2024: Concrete structure (RCC) 38%Dec 2025: Concrete structure (RCC) 38%Jul 2026: Concrete structure (RCC) 38%Oct 2026: Concrete structure (RCC) 38%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 75%Concrete structure (RCC) 38%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
75%38%0%100
75%38%0%100
75%38%0%100
75%38%0%68

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400069

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400069
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths3 yrs 6 mths
Possession date extendedNo3 of 5
Possession date (MahaRERA)Dec 2026Dec 2026
Concrete structure (RCC)38%100%
Units booked36%86%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Nicco Residency by Neelkamal Realty & Construction LLP is a 275-unit SRA-sanctioned project in Andheri East, Mumbai 400069, launched in April 2023 with possession due in December 2026. 100 units booked out of total 275 units. The concrete structure (RCC) is 38% complete.

Read full summary

Nicco Residency is an SRA-sanctioned project by Neelkamal Realty & Construction LLP in Andheri East, Mumbai 400069, registered with MahaRERA as P51800050433. It was launched in April 2023. It has 275 units in 4 buildings: 252 homes (1, 2, 3 and 4 BHK) and 23 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation 75% complete, structure (RCC) 38% complete, final finishes not started.

100 units booked out of total 275 units (36%).