Nicco Residency, Andheri East
by Neelkamal Realty & Construction LLP · Andheri East, Mumbai 400069 · Map
- Launched
- Apr 20233 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 38%Mid-construction
- Booked
- 100 of 27536%
- Buildings
- 41.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 2 BHK
- 165
- 3 BHK
- 65
- 4 BHK
- 21
- Other units
- 23
- Total units
- 275
- Buildings
- 4
- Land
- 1.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 75% | 38% | 0% | 100 | |
| 75% | 38% | 0% | 100 | |
| 75% | 38% | 0% | 100 | |
| 75% | 38% | 0% | 68 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400069
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 8 mths | 3 yrs 6 mths |
| Possession date extended | No | 3 of 5 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2026 |
| Concrete structure (RCC) | 38% | 100% |
| Units booked | 36% | 86% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Puri SeleQt, Andheri East
- Parleshwar Aangan, Andheri East
- Veena Synergy, Andheri East
- Acenza, Andheri East
- Atharv Aaradhyam, Andheri East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Puri SeleQt | March 2023 | December 2026 | 85% | 144 units booked out of 153 units for sale |
| Parleshwar Aangan | February 2023 | December 2026 | 100% | 63 units booked out of 124 units for sale |
| Veena Synergy | February 2023 | December 2026 | 100% | 171 units booked out of total 171 units |
| Acenza | January 2023 | May 2027 – Dec 2029 | 44% | 110 units booked out of total 241 units |
| Atharv Aaradhyam | August 2023 | April 2028 | 100% | 120 units booked out of 140 units for sale |
About this project
Nicco Residency by Neelkamal Realty & Construction LLP is a 275-unit SRA-sanctioned project in Andheri East, Mumbai 400069, launched in April 2023 with possession due in December 2026. 100 units booked out of total 275 units. The concrete structure (RCC) is 38% complete.
Read full summary
Nicco Residency is an SRA-sanctioned project by Neelkamal Realty & Construction LLP in Andheri East, Mumbai 400069, registered with MahaRERA as P51800050433. It was launched in April 2023. It has 275 units in 4 buildings: 252 homes (1, 2, 3 and 4 BHK) and 23 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation 75% complete, structure (RCC) 38% complete, final finishes not started.
100 units booked out of total 275 units (36%).