S S Vellozia CHS, Bhandup West

by Shree S S Infra Developers Private Limited · Bhandup West, Mumbai 400078 · Map

Launched
Sep 20235 yrs 3 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
100%Nearing possession
Booked
17 of 2028% · 13 in Jul 2026
Buildings
20.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
32
1 BHK
103
2 BHK
38
Other units
29
Total units
202
Buildings
2
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 74%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%17
100%74%0%13
0%0%0%11
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400078

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 3 mths5 yrs 3 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Dec 2028
Concrete structure (RCC)100%72%
Units booked8%72%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

S S Vellozia CHS by Shree S S Infra Developers Private Limited is a 202-unit SRA-sanctioned project in Bhandup West, Mumbai 400078, launched in September 2023 with possession due in December 2028. 17 units booked out of total 202 units. The concrete structure (RCC) is complete.

Read full summary

S S Vellozia CHS is an SRA-sanctioned project by Shree S S Infra Developers Private Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800052475. It was launched in September 2023. It has 202 units in 2 buildings: 173 homes (1 RK, 1 BHK and 2 BHK) and 29 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

17 units booked out of total 202 units (8%). Since the July 2026 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 74% to 100%.