Anant Siddhi, Bhandup West

by Shri Anantnathji Maharaj Jain Temple and Its Sadharan Funds · Bhandup West, Mumbai 400078 · Map

Launched
Sep 20234 yrs 6 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
81 of 10478% · 56 rehab units
Buildings
10.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale81 booked out of 104 units

Rehab56 units for existing members

Total 160 units. Rehab units are not for sale.

Project facts

1 BHK
58
2 BHK
56
3 BHK
24
4 BHK
1
Other units
21
Total units
160
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
0
Free-sale units
104
Rehab units
56

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 97%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 5%Jul 2026: Final finishes 15%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%81
100%100%15%75
100%97%5%52
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400078

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 6 mths5 yrs 4 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2028Dec 2028
Concrete structure (RCC)100%62%
Units booked (free sale)78%67%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Anant Siddhi by Shri Anantnathji Maharaj Jain Temple and Its Sadharan Funds is a 160-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, launched in September 2023 with possession due in March 2028. 81 units booked out of 104 units for sale. The concrete structure (RCC) is complete.

Read full summary

Anant Siddhi is a BMC-sanctioned project by Shri Anantnathji Maharaj Jain Temple and Its Sadharan Funds in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800052583. It was launched in September 2023. It has 160 units in 1 building: 139 homes (1, 2, 3 and 4 BHK) and 21 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 160 units, 104 are for sale and 56 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.

81 units booked out of 104 units for sale (78%). Since the July 2026 update, 6 more units have been booked.