Park View, Ghatkopar East
by Montage Infra Developers Private Limited (Earlier Known As Vinayak Developers) · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Jan 20243 yrs 11 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 88%Mid-construction
- Booked (free sale)
- 15 of 2171% · 12 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale15 booked out of 21 units
Rehab12 units for existing members
Total 33 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 18
- 2 BHK
- 4
- 3 BHK
- 11
- Total units
- 33
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 21
- Rehab units
- 12
- Reserved units
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 88% | 0% | 15 | |
| 100% | 82% | 0% | 5 | |
| 100% | 65% | 0% | 1 | |
| 100% | 45% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400077
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 11 mths | 4 yrs |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Feb 2028 |
| Concrete structure (RCC) | 88% | 92% |
| Units booked (free sale) | 71% | 25% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Koyal Geet Chsl, Ghatkopar East
- Shelton Crest, Ghatkopar East
- Vraj Emerald 60-Saikrupa, Ghatkopar East
- Kush Avenuee, Ghatkopar East
- Rdk Belvedere, Ghatkopar East
- Nav Ashish Premises Co-Operative Society Ltd, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Koyal Geet Chsl | November 2023 | December 2026 | 50% | – |
| Shelton Crest | November 2023 | September 2025 | 100% | 1 unit booked out of 11 units for sale |
| Vraj Emerald 60-Saikrupa | March 2024 | December 2029 | 66% | – |
| Kush Avenuee | October 2023 | April 2026 | 85% | 49 units booked out of total 58 units |
| Rdk Belvedere | September 2023 | December 2029 | 100% | 14 units booked out of 34 units for sale |
| Nav Ashish Premises Co-Operative Society Ltd | June 2024 | April 2029 | 100% | 1 unit booked out of 11 units for sale |
About this project
Park View by Montage Infra Developers Private Limited (Earlier Known As Vinayak Developers) is a 33-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in January 2024 with possession due in December 2027. 15 units booked out of 21 units for sale. The concrete structure (RCC) is 88% complete.
Read full summary
Park View is a BMC-sanctioned project by Montage Infra Developers Private Limited (Earlier Known As Vinayak Developers) in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800054171. It was launched in January 2024. It has 33 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 33 units, 21 are for sale and 12 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 88% complete, final finishes not started.
15 units booked out of 21 units for sale (71%). Since the July 2026 update, 10 more units have been booked and the reported concrete structure (RCC) has gone from 82% to 88%.