Vamanashram, Borivali West
by Vamanashram Co-Operative Housing Society Limited · Borivali West, Mumbai 400092 · Map
- Launched
- Sep 20232 yrs 6 mths originally promised
- Possession (MahaRERA)
- Mar 2028Extended by 2 yrs
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 19 of 2095% · 22 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale19 booked out of 20 units
Rehab22 units for existing members
Total 42 units. Rehab units are not for sale.
Project facts
- 1 RK
- 4
- 1 BHK
- 13
- 2 BHK
- 24
- 3 BHK
- 1
- Total units
- 42
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 20
- Rehab units
- 22
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 85% | 19 | |
| 100% | 100% | 85% | 19 | |
| 100% | 100% | 0% | 15 | |
| 100% | 95% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400092
Projects with 20–90 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 6 mths | 2 yrs 6 mths |
| Possession date extended | By 2 yrs | 3 of 6 |
| Possession date (MahaRERA) | Mar 2028 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 95% | 45% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Proposed Red On Plot Bearing Fp No 40 Of Tps III Village Borivali West Mumbai, Borivali West
- Rishabraj Aradhana, Borivali West
- Lekh Residency, Borivali West
- New Ashwin Chsl, Borivali West
- Palash, Borivali West
- Rita Palace Chsl, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Proposed Red On Plot Bearing Fp No 40 Of Tps III Village Borivali West Mumbai | August 2023 | September 2027 | 100% | 5 units booked out of 11 units for sale |
| Rishabraj Aradhana | October 2023 | July 2026 | 100% | 5 units booked out of 7 units for sale |
| Lekh Residency | October 2023 | December 2026 | 100% | 6 units booked out of 17 units for sale |
| New Ashwin Chsl | October 2023 | December 2026 | 95% | 17 units booked out of 51 units for sale |
| Palash | November 2023 | December 2026 | 100% | 32 units booked out of 38 units for sale |
| Rita Palace Chsl | November 2023 | December 2028 | 90% | – |
About this project
Vamanashram by Vamanashram Co-Operative Housing Society Limited is a 42-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in September 2023 with possession due in March 2028. 19 units booked out of 20 units for sale. The concrete structure (RCC) is complete.
Read full summary
Vamanashram is a BMC-sanctioned project by Vamanashram Co-Operative Housing Society Limited in Borivali West, Mumbai 400092, registered with MahaRERA as P51800052574. It was launched in September 2023. It has 42 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 42 units, 20 are for sale and 22 are rehab units for existing members.
Its registered possession date is March 2028, extended by 2 years from the original March 2026. Construction: excavation complete, structure (RCC) complete, final finishes 85% complete.
19 units booked out of 20 units for sale (95%).