New Ashwin Chsl, Borivali West
by Ossia Buildcon Private Limited · Borivali West, Mumbai 400092 · Map
- Launched
- Oct 20233 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 95%Mid-construction
- Booked (free sale)
- 17 of 5133% · 39 rehab units
- Buildings
- 20.3 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale17 booked out of 51 units
Rehab39 units for existing members
Total 90 units. Rehab units are not for sale.
Project facts
- 1 RK
- 4
- 1 BHK
- 41
- 2 BHK
- 31
- Other units
- 14
- Total units
- 90
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 3
- Free-sale units
- 51
- Rehab units
- 39
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 25% | 17 | |
| 100% | 90% | 0% | 4 | |
| 100% | 0% | 0% | 3 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400092
Projects with 30–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 2 mths | 2 yrs 4 mths |
| Possession date extended | No | 4 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Mar 2027 |
| Concrete structure (RCC) | 95% | 100% |
| Units booked (free sale) | 33% | 66% |
| MahaRERA complaints (filed by or against the builder) | 3 | 0 |
The 6 projects
- Lekh Residency, Borivali West
- Shraddha Skyline, Borivali West
- Rita Palace Chsl, Borivali West
- Palash, Borivali West
- Vamanashram, Borivali West
- State Sector Bank Employees Chs Ltd Kailas Building, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Lekh Residency | October 2023 | December 2026 | 100% | 6 units booked out of 17 units for sale |
| Shraddha Skyline | October 2023 | December 2026 | 96% | 43 units booked out of 65 units for sale |
| Rita Palace Chsl | November 2023 | December 2028 | 90% | – |
| Palash | November 2023 | December 2026 | 100% | 32 units booked out of 38 units for sale |
| Vamanashram | September 2023 | March 2028 | 100% | 19 units booked out of 20 units for sale |
| State Sector Bank Employees Chs Ltd Kailas Building | June 2023 | July 2027 | 100% | 16 units booked out of 43 units for sale |
About this project
New Ashwin Chsl by Ossia Buildcon Private Limited is a 90-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in October 2023 with possession due in December 2026. 17 units booked out of 51 units for sale. The concrete structure (RCC) is 95% complete.
Read full summary
New Ashwin Chsl is a BMC-sanctioned project by Ossia Buildcon Private Limited in Borivali West, Mumbai 400092, registered with MahaRERA as P51800053401. It was launched in October 2023. It has 90 units in 2 buildings: 76 homes (1 RK, 1 BHK and 2 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 90 units, 51 are for sale and 39 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 95% complete, final finishes 25% complete.
17 units booked out of 51 units for sale (33%). Since the July 2026 update, 13 more units have been booked and the reported concrete structure (RCC) has gone from 90% to 95%.