Tru Gardenia, Andheri West
by Tru Sun-Vision Realty LLP · Andheri West, Mumbai 400053 · Map
- Launched
- Sep 20233 yrs 10 mths originally promised
- Possession (MahaRERA)
- Apr 2029Extended by 1 yr 9 mths
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 15 of 7021% · 40 rehab units
- Buildings
- 20.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale15 booked out of 70 units
Rehab40 units for existing members
Total 110 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 2 BHK
- 105
- 4 BHK
- 1
- 5+ BHK
- 3
- Total units
- 110
- Buildings
- 2
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 70
- Rehab units
- 40
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 15 | |
| 100% | 0% | 0% | – | |
| 95% | 0% | 0% | – | |
| 75% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400053
Projects with 50–250 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 10 mths | 3 yrs 9 mths |
| Possession date extended | By 1 yr 9 mths | 0 of 3 |
| Possession date (MahaRERA) | Apr 2029 | Mar 2027 |
| Concrete structure (RCC) | 0% | 95% |
| Units booked (free sale) | 21% | 73% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Lashkaria Indrasukh, Andheri West
- Mantri Our Home, Andheri West
- Gurukrupa Dhyanam, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Lashkaria Indrasukh | September 2023 | December 2028 | 95% | 47 units booked out of 64 units for sale |
| Mantri Our Home | June 2023 | March 2027 | 0% | 38 units booked out of 54 units for sale |
| Gurukrupa Dhyanam | April 2024 | March 2027 | 100% | 82 units booked out of total 111 units |
About this project
Tru Gardenia by Tru Sun-Vision Realty LLP is a 110-unit MHADA-sanctioned project in Andheri West, Mumbai 400053, launched in September 2023 with possession due in April 2029. 15 units booked out of 70 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Tru Gardenia is a MHADA-sanctioned project by Tru Sun-Vision Realty LLP in Andheri West, Mumbai 400053, registered with MahaRERA as P51800052584. It was launched in September 2023. It has 110 units in 2 buildings, with 1, 2, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 110 units, 70 are for sale and 40 are rehab units for existing members.
Its registered possession date is April 2029, extended by 1 year 9 months from the original July 2027. Construction: excavation complete, structure (RCC) not started, final finishes not started.
15 units booked out of 70 units for sale (21%).