Mantri Our Home, Andheri West

by Pentagon Premises Private Limited · Andheri West, Mumbai 400053 · Map

Launched
Jun 20233 yrs 9 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
0%Early stage
Booked (free sale)
38 of 5470% · 63 rehab units
Buildings
20.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale38 booked out of 54 units

Rehab63 units for existing members

Total 117 units. Rehab units are not for sale.

Project facts

2 BHK
78
3 BHK
36
Other units
3
Total units
117
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
54
Rehab units
63

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%38
0%0%0%38
0%0%0%24
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400053

Projects with 50–250 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400053
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths5 yrs
Possession date extendedNo1 of 4
Possession date (MahaRERA)Mar 2027Feb 2029
Concrete structure (RCC)0%30%
Units booked (free sale)70%73%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Mantri Our Home by Pentagon Premises Private Limited is a 117-unit BMC-sanctioned project in Andheri West, Mumbai 400053, launched in June 2023 with possession due in March 2027. 38 units booked out of 54 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Mantri Our Home is a BMC-sanctioned project by Pentagon Premises Private Limited in Andheri West, Mumbai 400053, registered with MahaRERA as P51800051596. It was launched in June 2023. It has 117 units in 2 buildings: 114 homes (2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 117 units, 54 are for sale and 63 are rehab units for existing members.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

38 units booked out of 54 units for sale (70%).