Skip to main content

Parshva Avenue, Kandivali West

by Aarsh Construction · Kandivali West, Mumbai 400067 · Map

Launched
Sep 20234 yrs 3 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
20 of 4149% · 32 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale20 booked out of 41 units

Rehab32 units for existing members

Total 73 units. Rehab units are not for sale.

Project facts

1 BHK
14
2 BHK
49
3 BHK
9
4 BHK
1
Total units
73
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
41
Rehab units
32

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 48%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 30%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 100%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%30%20
100%100%30%20
100%100%0%14
100%48%0%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 3 mths2 yrs 10 mths
Possession date extendedNo3 of 6
Possession date (MahaRERA)Dec 2027Sep 2027
Concrete structure (RCC)100%86%
Units booked (free sale)49%73%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Parshva Avenue by Aarsh Construction is a 73-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in September 2023 with possession due in December 2027. 20 units booked out of 41 units for sale. The concrete structure (RCC) is complete.

Read full summary

Parshva Avenue is a BMC-sanctioned project by Aarsh Construction in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800052612. It was launched in September 2023. It has 73 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 73 units, 41 are for sale and 32 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.

20 units booked out of 41 units for sale (49%).