Estella, Kandivali West
by V City Builders & Developers LLP · Kandivali West, Mumbai 400067 · Map
- Launched
- Jul 20231 yr 11 mths originally promised
- Possession (MahaRERA)
- Jun 2028Extended by 3 yrs
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 65 of 7686% · 51 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale65 booked out of 76 units
Rehab51 units for existing members
Total 127 units. Rehab units are not for sale.
Project facts
- 1 RK
- 3
- 1 BHK
- 2
- 2 BHK
- 53
- 3 BHK
- 16
- Other units
- 53
- Total units
- 127
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 76
- Rehab units
- 51
- Reserved units
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 50% | 65 | |
| 100% | 88% | 50% | 64 | |
| 100% | 65% | 50% | 64 | |
| 100% | 55% | 33% | 5 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 11 mths | 3 yrs 7 mths |
| Possession date extended | By 3 yrs | 2 of 6 |
| Possession date (MahaRERA) | Jun 2028 | Jul 2027 |
| Concrete structure (RCC) | 90% | 92% |
| Units booked (free sale) | 86% | 47% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Charkop Rakesh Co. Op. Hsg. Soceity Ltd, Kandivali West
- J-24 Mahavir Nagar CHS Ltd, Kandivali West
- Charkop 1 Abhilasha Co Operative Housing Society Limited, Kandivali West
- Parshva Avenue, Kandivali West
- Neminavkar Dudhreshi, Kandivali West
- Sunder Baug Chsl, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Charkop Rakesh Co. Op. Hsg. Soceity Ltd | July 2023 | December 2027 | 65% | 17 units booked out of 52 units for sale |
| J-24 Mahavir Nagar CHS Ltd | June 2023 | July 2027 | 100% | 12 units booked out of 43 units for sale |
| Charkop 1 Abhilasha Co Operative Housing Society Limited | June 2023 | December 2026 | 100% | 81 units booked out of 87 units for sale |
| Parshva Avenue | September 2023 | December 2027 | 100% | 20 units booked out of 41 units for sale |
| Neminavkar Dudhreshi | October 2023 | June 2027 | 83% | 73 units booked out of 83 units for sale |
| Sunder Baug Chsl | April 2023 | December 2026 | 70% | 24 units booked out of total 54 units |
About this project
Estella by V City Builders & Developers LLP is a 127-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in July 2023 with possession due in June 2028. 65 units booked out of 76 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Estella is an SRA-sanctioned project by V City Builders & Developers LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800052152. It was launched in July 2023. It has 127 units in 1 building: 74 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 53 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 127 units, 76 are for sale and 51 are rehab units for existing members.
Its registered possession date is June 2028, extended by 3 years from the original June 2025. Construction: excavation complete, structure (RCC) 90% complete, final finishes 50% complete.
65 units booked out of 76 units for sale (86%). Since the July 2026 update, 1 more unit has been booked, the reported concrete structure (RCC) has gone from 88% to 90% and the possession date has moved from June 2026 to June 2028.