Neminavkar Dudhreshi, Kandivali West

by Raj Skyline & Kcd Builders Private Limited · Kandivali West, Mumbai 400067 · Map

Launched
Oct 20232 yrs 8 mths originally promised
Possession (MahaRERA)
Jun 2027Extended by 1 yr
Concrete structure
83%Mid-construction
Booked (free sale)
73 of 8388%
Buildings
10.3 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale73 booked out of 83 units

Land-owner share3 units, not for sale

Total 86 units. Land-owner units are not for sale.

Project facts

1 BHK
36
2 BHK
25
Other units
25
Total units
86
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
2
Reserved units
9
Free-sale units
83
Land-owner share (not for sale)
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)83%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 87%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 16%Jul 2026: Concrete structure (RCC) 83%Oct 2026: Concrete structure (RCC) 83%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 83%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%83%0%73
100%83%0%64
100%16%0%–
87%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 8 mths3 yrs
Possession date extendedBy 1 yr2 of 6
Possession date (MahaRERA)Jun 2027Sep 2027
Concrete structure (RCC)83%100%
Units booked (free sale)88%59%
MahaRERA complaints (filed by or against the builder)20

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Neminavkar Dudhreshi by Raj Skyline & Kcd Builders Private Limited is an 86-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in October 2023 with possession due in June 2027. 73 units booked out of 83 units for sale. The concrete structure (RCC) is 83% complete.

Read full summary

Neminavkar Dudhreshi is a BMC-sanctioned project by Raj Skyline & Kcd Builders Private Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800053058. It was launched in October 2023. It has 86 units in 1 building: 61 homes (1 and 2 BHK) and 25 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 86 units, 83 are for sale and 3 are the land-owner's share, not for sale.

Its registered possession date is June 2027, extended by 1 year from the original June 2026. Construction: excavation complete, structure (RCC) 83% complete, final finishes not started.

73 units booked out of 83 units for sale (88%). Since the July 2026 update, 9 more units have been booked.