Ruparel Crest, Kurla East

by Bharat Mahan Developers & Builders · Kurla East, Mumbai 400024 · Map

Launched
Sep 20232 yrs 3 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
89%Mid-construction
Booked
230 of 27783%
Buildings
30.8 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
163
2 BHK
51
3 BHK
34
Other units
29
Total units
277
Buildings
3
Land
0.8 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)89%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 89%Oct 2026: Concrete structure (RCC) 89%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 89%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%89%0%230
100%89%0%230
0%0%0%230
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400024

Projects with 100–500 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400024
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 3 mths3 yrs 6 mths
Possession date extendedBy 1 yr1 of 4
Possession date (MahaRERA)Dec 2026Dec 2026
Concrete structure (RCC)89%90%
Units booked83%92%
MahaRERA complaints (filed by or against the builder)40

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Ruparel Crest by Bharat Mahan Developers & Builders (Ruparel) is a 277-unit SRA-sanctioned project in Kurla East, Mumbai 400024, launched in September 2023 with possession due in December 2026. 230 units booked out of total 277 units. The concrete structure (RCC) is 89% complete.

Read full summary

Ruparel Crest is an SRA-sanctioned project by Bharat Mahan Developers & Builders in Kurla East, Mumbai 400024, registered with MahaRERA as P51800052788. It was launched in September 2023. It has 277 units in 3 buildings: 248 homes (1, 2 and 3 BHK) and 29 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) 89% complete, final finishes not started.

230 units booked out of total 277 units (83%).

Ruparel's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA28
Total units across these projects6,570
Completed without extending the possession date0
Completed after an extension1
Lapsed12
Under construction15
Possession date extended on the builder's application14
Typical time from launch to 100% structure5 years 9 months
MahaRERA complaints (filed by or against the builder), all Ruparel projects872 (22 of 28 projects)

See all Ruparel projects →