Kurla Vijay Rahivashi Sangh Co-op. Hsg.Soc.Ltd, Kurla East
by Vikas Narayan Raikar · Kurla East, Mumbai 400024 · Map
- Launched
- Apr 20245 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 80%Mid-construction
- Booked (free sale)
- 29 of 4860% · 155 rehab units
- Buildings
- 10.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale29 booked out of 48 units
Rehab155 units for existing members
Total 203 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 186
- Other units
- 17
- Total units
- 203
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 48
- Rehab units
- 155
- Reserved units
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 0% | 29 | |
| 100% | 80% | 0% | 29 | |
| 100% | 80% | 0% | 29 | |
| 100% | 85% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400024
Projects with 90–400 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 8 mths | 2 yrs 9 mths |
| Possession date extended | No | 1 of 3 |
| Possession date (MahaRERA) | Dec 2029 | Mar 2027 |
| Concrete structure (RCC) | 80% | 100% |
| Units booked (free sale) | 60% | 90% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Sayba Tulip, Kurla East
- Sayba Crystal, Kurla East
- Ruparel Crest, Kurla East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sayba Tulip | June 2024 | March 2027 | 100% | 110 units booked out of 119 units for sale |
| Sayba Crystal | July 2024 | May 2027 | 100% | 131 units booked out of 145 units for sale |
| Ruparel Crest | September 2023 | December 2026 | 89% | 230 units booked out of total 277 units |
About this project
Kurla Vijay Rahivashi Sangh Co-op. Hsg.Soc.Ltd by Vikas Narayan Raikar is a 203-unit SRA-sanctioned project in Kurla East, Mumbai 400024, launched in April 2024 with possession due in December 2029. 29 units booked out of 48 units for sale. The concrete structure (RCC) is 80% complete.
Read full summary
Kurla Vijay Rahivashi Sangh Co-op. Hsg.Soc.Ltd is an SRA-sanctioned project by Vikas Narayan Raikar in Kurla East, Mumbai 400024, registered with MahaRERA as P51800055918. It was launched in April 2024. It has 203 units in 1 building: 186 homes (1 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 203 units, 48 are for sale and 155 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.
29 units booked out of 48 units for sale (60%).