Shraddha Skyline, Borivali West

by Shraddha Developers & Realtors · Borivali West, Mumbai 400092 · Map

Launched
Oct 20233 yrs 2 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
96%Mid-construction
Booked (free sale)
43 of 6566% · 95 rehab units
Buildings
21.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale43 booked out of 65 units

Rehab95 units for existing members

Total 160 units. Rehab units are not for sale.

Project facts

1 BHK
23
2 BHK
51
3 BHK
51
4 BHK
31
Other units
4
Total units
160
Buildings
2
Land
1.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
65
Rehab units
95

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)96%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 90%Dec 2025: Excavation 90%Jul 2026: Excavation 90%Oct 2026: Excavation 90%Dec 2024: Concrete structure (RCC) 18%Dec 2025: Concrete structure (RCC) 69%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 96%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Concrete structure (RCC) 96%Excavation 90%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%96%0%43
90%90%0%44
90%69%0%28
90%18%0%19

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400092

Projects with 70–350 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 2 mths4 yrs 6 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2026Dec 2027
Concrete structure (RCC)96%90%
Units booked (free sale)66%46%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Shraddha Skyline by Shraddha Developers & Realtors is a 160-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in October 2023 with possession due in December 2026. 43 units booked out of 65 units for sale. The concrete structure (RCC) is 96% complete.

Read full summary

Shraddha Skyline is a BMC-sanctioned project by Shraddha Developers & Realtors in Borivali West, Mumbai 400092, registered with MahaRERA as P51800053170. It was launched in October 2023. It has 160 units in 2 buildings: 156 homes (1, 2, 3 and 4 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 160 units, 65 are for sale and 95 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation 90% complete, structure (RCC) 96% complete, final finishes not started.

43 units booked out of 65 units for sale (66%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 90% to 96%.

Shraddha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA53
Total units across these projects9,707
Completed without extending the possession date16
Completed after an extension4
Lapsed5
Under construction28
Possession date extended on the builder's application18
Typical time from launch to 100% structure4 years
MahaRERA complaints (filed by or against the builder), all Shraddha projects14 (11 of 53 projects)

See all Shraddha projects →